909 E FLOWER AVE 90291

Certificate Information: 909 E FLOWER AVE 90291

Application / Permit
21010-10000-00319
Plan Check / Job No.
B21LA01016
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2 story detached ADU on top of new garage. Existing garage to be demolished.
Permit Issued
Issued on 7/8/2022
Issuing Office
Current Status
CofO Issued on 12/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 JOE VO
Corrections Issued 2/18/2021 JOE VO
Quality Review Completed 2/26/2021 HERNAN ARREOLA
Applicant returned to address corrections 9/14/2021 JOE VO
Applicant returned to address corrections 9/22/2021 JOE VO
Applicant returned to address corrections 3/16/2022 JOE VO
Plan Check Approved 4/9/2022 JOE VO
Issued 7/8/2022 APPLICANT
CofO in Progress 12/3/2024 HERBERT GIRON
CofO Issued 12/9/2024 RICHARD STEINBACH
Permit Finaled 12/9/2024 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/27/2021 TRACY TATE
Hydrant and Access approval Cleared 9/21/2021 MATTHEW CRAIG
Sewer availability Cleared 9/27/2021 TRACY TATE
Low Impact Development Cleared 1/31/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 2/2/2022 TRACY TATE
Address approval Cleared 2/3/2022 TRACY TATE
Permit Cleared 2/3/2022 TRACY TATE
Specific Plan Cleared 2/25/2022 PEDRO AYALA

Contact Information

Contractor F S Design & Construction Inc; Lic. No.: 727272-B       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/13/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 9/15/2022 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 9/26/2022 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Corrections Issued DAVID FEILER
Special/Order Compliance 10/26/2022 Partial Inspection CLAYTON GRAHAM
Deputy Steel/Welding 10/31/2022 Approved DAVID FEILER
Deputy Wood Construction 10/31/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Partial Approval DAVID FEILER
ELECTRICAL-Rough 3/20/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 3/20/2023 Approved EVAN COOPER
Drywall Nailing 3/28/2023 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Partial Approval EVAN COOPER
HVAC-Rough 3/28/2023 Approved EVAN COOPER
Verify Sprinkler Sign Off 3/28/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 4/7/2023 Approved JEREMY TODD
Green Building Rough 4/7/2023 Approved JEREMY TODD
Interior/Exterior Lathing 4/27/2023 Partial Approval EVAN COOPER
Insulation 5/4/2023 Corrections Issued HERBERT GIRON
Insulation 5/8/2023 Approved EVAN COOPER
Drywall Nailing 5/16/2023 Approved EVAN COOPER
Interior/Exterior Lathing 6/22/2023 Approved EVAN COOPER
ELECTRICAL-Final 11/16/2023 Corrections Issued HERBERT GIRON
Underground Mechanical 11/16/2023 Approved HERBERT GIRON
ELECTRICAL-Final 11/27/2023 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 11/27/2023 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Final 11/27/2023 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 12/1/2023 Corrections Issued HERBERT GIRON
HVAC-Final 12/1/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 12/1/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 1/11/2024 Corrections Issued HERBERT GIRON
HVAC-Final 1/11/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 1/11/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 2/12/2024 Approved HERBERT GIRON
HVAC-Final 2/12/2024 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 2/12/2024 Not Ready for Inspection HERBERT GIRON
HVAC-Final 2/23/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 2/23/2024 Approved HERBERT GIRON
Final 7/9/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 7/9/2024 Approved HERBERT GIRON
Green Building Final 7/9/2024 Approved HERBERT GIRON
HVAC-Final 7/9/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 7/9/2024 SGSOV Not Required HERBERT GIRON
Service/Power Release 7/9/2024 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 7/9/2024 Approved HERBERT GIRON
Service/Power Release 7/12/2024 Approved HERBERT GIRON
Final 12/3/2024 OK to Issue CofO HERBERT GIRON