909 E FLOWER AVE 90291
Certificate Information: 909 E FLOWER AVE 90291
- Application / Permit
- 21010-10000-00319
- Plan Check / Job No.
- B21LA01016
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2 story detached ADU on top of new garage. Existing garage to be demolished.
- Permit Issued
- Issued on 7/8/2022
- Issuing Office
- Current Status
- CofO Issued on 12/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | JOE VO |
| Corrections Issued | 2/18/2021 | JOE VO |
| Quality Review Completed | 2/26/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 9/14/2021 | JOE VO |
| Applicant returned to address corrections | 9/22/2021 | JOE VO |
| Applicant returned to address corrections | 3/16/2022 | JOE VO |
| Plan Check Approved | 4/9/2022 | JOE VO |
| Issued | 7/8/2022 | APPLICANT |
| CofO in Progress | 12/3/2024 | HERBERT GIRON |
| CofO Issued | 12/9/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/9/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2021 | TRACY TATE |
| Hydrant and Access approval | Cleared | 9/21/2021 | MATTHEW CRAIG |
| Sewer availability | Cleared | 9/27/2021 | TRACY TATE |
| Low Impact Development | Cleared | 1/31/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 2/2/2022 | TRACY TATE |
| Address approval | Cleared | 2/3/2022 | TRACY TATE |
| Permit | Cleared | 2/3/2022 | TRACY TATE |
| Specific Plan | Cleared | 2/25/2022 | PEDRO AYALA |
Contact Information
| Contractor | F S Design & Construction Inc; Lic. No.: 727272-B | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/13/2022 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 9/15/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 9/26/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Corrections Issued | DAVID FEILER |
| Special/Order Compliance | 10/26/2022 | Partial Inspection | CLAYTON GRAHAM |
| Deputy Steel/Welding | 10/31/2022 | Approved | DAVID FEILER |
| Deputy Wood Construction | 10/31/2022 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 3/20/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 3/20/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 3/28/2023 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 3/28/2023 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 3/28/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 4/7/2023 | Approved | JEREMY TODD |
| Green Building Rough | 4/7/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 4/27/2023 | Partial Approval | EVAN COOPER |
| Insulation | 5/4/2023 | Corrections Issued | HERBERT GIRON |
| Insulation | 5/8/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 5/16/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/22/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 11/16/2023 | Corrections Issued | HERBERT GIRON |
| Underground Mechanical | 11/16/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/27/2023 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 11/27/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Final | 11/27/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 12/1/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 12/1/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 12/1/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 1/11/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 1/11/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 1/11/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 2/12/2024 | Approved | HERBERT GIRON |
| HVAC-Final | 2/12/2024 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 2/12/2024 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 2/23/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 2/23/2024 | Approved | HERBERT GIRON |
| Final | 7/9/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 7/9/2024 | Approved | HERBERT GIRON |
| Green Building Final | 7/9/2024 | Approved | HERBERT GIRON |
| HVAC-Final | 7/9/2024 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 7/9/2024 | SGSOV Not Required | HERBERT GIRON |
| Service/Power Release | 7/9/2024 | Not Ready for Inspection | HERBERT GIRON |
| Smoke Detectors | 7/9/2024 | Approved | HERBERT GIRON |
| Service/Power Release | 7/12/2024 | Approved | HERBERT GIRON |
| Final | 12/3/2024 | OK to Issue CofO | HERBERT GIRON |