7946 N AURA AVE 91335

Certificate Information: 7946 N AURA AVE 91335

Application / Permit
21010-10000-00315
Plan Check / Job No.
B21LA00990
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)&(d)
Permit Issued
Issued on 7/30/2021
Issuing Office
Current Status
CofO Issued on 9/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 LAMAR DAVIS
Corrections Issued 2/18/2021 LAMAR DAVIS
Quality Review Completed 2/26/2021 HERNAN ARREOLA
Applicant returned to address corrections 3/18/2021 LAMAR DAVIS
Applicant returned to address corrections 5/3/2021 LAMAR DAVIS
Applicant returned to address corrections 6/9/2021 LAMAR DAVIS
Plan Check Approved 6/9/2021 LAMAR DAVIS
Issued 7/30/2021 APPLICANT
CofO in Progress 8/26/2022 SEAN WIRCH
Permit Finaled 9/10/2022 MICHAEL SMITH
CofO Issued 9/10/2022 MICHAEL SMITH
Permit Finaled 9/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/22/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 2/23/2021 GABRIEL ROBLES
Sewer availability Cleared 2/23/2021 GABRIEL ROBLES
Miscellaneous Cleared 3/17/2021 LAMAR DAVIS
Hydrant and Access approval Cleared 4/15/2021 JOHN CONNEALLY
Low Impact Development Cleared 5/11/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 5/21/2021 GABRIEL ROBLES

Contact Information

Contractor S P S Construction; Lic. No.: 683130-B 10153 1/2 RIVERSIDE DR   APT 463    TOLUCA LAKE, CA 91602
Engineer Crook,, Barrett Cameron; Lic. No.: C57196 2036 CREEK RD      KITTY HAWK, NC 27949

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/23/2021 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 8/27/2021 Partial Approval TROY SANDERS
Underground Mechanical 8/27/2021 Approved TROY SANDERS
Footing/Foundation/Slab 9/3/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/23/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 11/8/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 11/8/2021 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Approved VINCENT HANLEY
HVAC-Rough 11/8/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 11/8/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/16/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 11/16/2021 Approved VINCENT HANLEY
Green Building Rough 11/16/2021 Approved VINCENT HANLEY
HVAC-Rough 11/16/2021 Approved VINCENT HANLEY
Underground Mechanical 1/26/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 3/10/2022 Approved VINCENT HANLEY
Green Building Rough 3/10/2022 Approved VINCENT HANLEY
Insulation 3/16/2022 Conditional Approval JUSTIN HAWLEY
Interior/Exterior Lathing 3/16/2022 Partial Approval JUSTIN HAWLEY
Drywall Nailing 3/23/2022 Approved MORRIS JACKSON
Shower Pan 4/4/2022 Corrections Issued JUSTIN HAWLEY
Interior/Exterior Lathing 4/7/2022 Approved VINCENT HANLEY
Shower Pan 4/7/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/11/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 8/25/2022 Approved SEAN WIRCH
Final 8/25/2022 OK to Issue CofO SEAN WIRCH
Gas Test 8/25/2022 Approved SEAN WIRCH
Green Building Final 8/25/2022 Approved SEAN WIRCH
HVAC-Final 8/25/2022 Approved SEAN WIRCH
PLUMBING-Final 8/25/2022 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 8/25/2022 SGSOV Approved SEAN WIRCH
Service/Power Release 8/25/2022 Approved SEAN WIRCH
Smoke Detectors 8/25/2022 Approved SEAN WIRCH