7525 N BECK AVE 91605

Certificate Information: 7525 N BECK AVE 91605

Application / Permit
21010-10000-00289
Plan Check / Job No.
B21LA00967
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) REC. ROOM. 3 OF 3
Permit Issued
Issued on 8/19/2021
Issuing Office
Current Status
CofO Issued on 4/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 SERGIO GUTIERREZ
Corrections Issued 2/3/2021 SERGIO GUTIERREZ
Quality Review Completed 2/10/2021 TIEN JEN WANG
Building Plans Picked Up 2/19/2021 APPLICANT
Applicant returned to address corrections 7/16/2021 SERGIO GUTIERREZ
Plan Check Approved 7/21/2021 SERGIO GUTIERREZ
Issued 8/19/2021 APPLICANT
CofO in Progress 4/20/2023 JOHN HAYES
Permit Finaled 4/24/2023 MICHAEL SMITH
CofO Issued 4/24/2023 MICHAEL SMITH
Permit Finaled 4/24/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/9/2021 ADRIAN CASTRO
Sewer availability Cleared 3/9/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/19/2021 ADRIAN CASTRO
Construction near power lines Cleared 4/2/2021 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/28/2021 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 12/28/2021 Corrections Issued JACK KARGODORIAN
Insulation 1/13/2022 Partial Approval DEANDRE HOFFMAN
BUILDING-Rough-Frame 6/3/2022 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 6/3/2022 Approved JACK KARGODORIAN
Green Building Rough 6/3/2022 Approved JACK KARGODORIAN
HVAC-Rough 6/3/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 6/3/2022 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 6/3/2022 Approved JACK KARGODORIAN
ELECTRICAL-Rough 6/10/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 6/10/2022 Approved JACK KARGODORIAN
Wood Frame 6/10/2022 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 6/21/2022 Approved JOHN HAYES
Interior/Exterior Lathing 6/21/2022 Partial Approval JOHN HAYES
Rough-Elec/Plmb/HVAC 6/21/2022 Approved JOHN HAYES
Insulation 6/30/2022 Approved JACK KARGODORIAN
Drywall Nailing 7/15/2022 Approved JOHN HAYES
Footing/Foundation/Slab 12/1/2022 Not Ready for Inspection JOHN HAYES
Insulation 12/1/2022 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 12/1/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 12/1/2022 Not Ready for Inspection JOHN HAYES
Wood Frame 12/1/2022 Not Ready for Inspection JOHN HAYES
Final 1/9/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 1/9/2023 Not Ready for Inspection JOHN HAYES
Green Building Final 1/9/2023 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/9/2023 SGSOV Not Ready JOHN HAYES
Service/Power Release 1/9/2023 Not Ready for Inspection JOHN HAYES
Smoke Detectors 1/9/2023 Not Ready for Inspection JOHN HAYES
Final 4/19/2023 OK to Issue CofO JOHN HAYES
Footing/Foundation/Slab 4/19/2023 Approved JOHN HAYES
Green Building Final 4/19/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 4/19/2023 SGSOV Approved JOHN HAYES
Service/Power Release 4/19/2023 Approved JOHN HAYES
Smoke Detectors 4/19/2023 Approved JOHN HAYES