519 1/4-1/2 W 41ST PL 90037
Certificate Information: 519 1/4-1/2 W 41ST PL 90037
- Application / Permit
- 21010-10000-00275
- Plan Check / Job No.
- B21LA00944
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX WITH ATTACHED GARAGE (FRONT)
- Permit Issued
- Issued on 1/24/2022
- Issuing Office
- Current Status
- CofO Issued on 1/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2021 | STARR CHEN |
| Corrections Issued | 2/28/2021 | STARR CHEN |
| Quality Review Completed | 3/3/2021 | JASON HEALEY |
| Building Plans Picked Up | 3/9/2021 | APPLICANT |
| Applicant returned to address corrections | 5/7/2021 | STARR CHEN |
| Applicant returned to address corrections | 6/10/2021 | STARR CHEN |
| Applicant returned to address corrections | 11/4/2021 | STARR CHEN |
| Plan Check Approved | 11/19/2021 | STARR CHEN |
| Issued | 1/24/2022 | APPLICANT |
| CofO in Progress | 12/28/2022 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
| CofO Issued | 1/7/2023 | DEROLD HAUFF |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 3/5/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2021 | CELINA MORENO |
| Frnt yard landscape/Water mgmt | Cleared | 4/23/2021 | LAUREN PADICK |
| Sewer availability | Cleared | 5/4/2021 | WALLIE JONG |
| Address approval | Cleared | 5/7/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 5/14/2021 | JOHN CONNEALLY |
| Trees in Parkway | Cleared | 5/20/2021 | JOHN KIM |
| Low Impact Development | Cleared | 10/22/2021 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 10/28/2021 | CELINA MORENO |
Contact Information
| Architect | Feagins,, Larry; Lic. No.: C27009 | 669 N THIRD AVENUE UPLAND, CA 91786 |
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/28/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 1/28/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 2/3/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/12/2022 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 7/12/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 7/12/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 7/12/2022 | Approved | SABAS ALONSO |
| MERV13>=Rough | 7/12/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 7/12/2022 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 7/12/2022 | Approved | SABAS ALONSO |
| Insulation | 7/20/2022 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/28/2022 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/28/2022 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 9/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 9/16/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 9/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/16/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Rec and Parks Fee Memo | 9/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/19/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/16/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 11/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/16/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/16/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/22/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/22/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/27/2022 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |