601-601 1/2 W 41ST PL 90037
Certificate Information: 601-601 1/2 W 41ST PL 90037
- Application / Permit
- 21010-10000-00270
- Plan Check / Job No.
- B21LA00942
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 3-STORY DUPLEX WITH ATTACHED ADU PER LAMC 12.22 A 33 AND ATTACHED CARPORT (REAR OF LOT)
- Permit Issued
- Issued on 1/30/2022
- Issuing Office
- Current Status
- CofO Issued on 4/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 3/4/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 3/5/2021 | JASON HEALEY |
| Building Plans Picked Up | 3/23/2021 | APPLICANT |
| Applicant returned to address corrections | 5/5/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 12/21/2021 | MAHNAZ NOURHASHEMI |
| Issued | 1/30/2022 | APPLICANT |
| CofO in Progress | 4/15/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 4/22/2023 | DEROLD HAUFF |
| Permit Finaled | 4/22/2023 | DEROLD HAUFF |
| CofO Issued | 4/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2021 | JEANIE LAM |
| Permit | Cleared | 3/8/2021 | JEANIE LAM |
| Sewer availability | Cleared | 3/8/2021 | JEANIE LAM |
| Trees in Parkway | Cleared | 4/7/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 5/7/2021 | MATTHEW CRAIG |
| Highway dedication | Cleared | 5/11/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 11/17/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/18/2021 | JEANIE LAM |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/18/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/18/2022 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 2/25/2022 | Approved | HORACE FULTZ |
| Deputy Reinf. Concrete | 2/28/2022 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/14/2022 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 7/14/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 7/14/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 7/14/2022 | Approved | SABAS ALONSO |
| Insulation | 7/18/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 9/27/2022 | Partial Approval | SABAS ALONSO |
| Sewer | 9/27/2022 | Approved | SABAS ALONSO |
| Verify Rec and Parks Fee Memo | 9/27/2022 | Not Ready for Inspection | SABAS ALONSO |
| Gas Test | 11/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/1/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/1/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/5/2022 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/5/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/31/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/31/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/31/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 3/31/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/31/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/31/2023 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 3/31/2023 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 4/3/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/4/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/14/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |