5451 S BRYNHURST AVE 90043
Certificate Information: 5451 S BRYNHURST AVE 90043
- Application / Permit
- 21010-10000-00264
- Plan Check / Job No.
- B21LA00923
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU AT REAR OF LOT PER LAMC 12.22 A 33 (c) AND (d)
- Permit Issued
- Issued on 11/22/2021
- Issuing Office
- Current Status
- CofO Issued on 11/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2021 | RICARDO RAMIREZ |
| Corrections Issued | 2/2/2021 | RICARDO RAMIREZ |
| Plan Check Approved | 10/27/2021 | DANIEL SANJUAN |
| Issued | 11/22/2021 | APPLICANT |
| Building Plans Picked Up | 11/24/2021 | APPLICANT |
| CofO in Progress | 10/7/2022 | ANTHONY EGSON |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
| CofO Issued | 11/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/5/2021 | RIDWAN HARDY |
| Address approval | Cleared | 5/21/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2021 | JEANIE LAM |
| Sewer availability | Cleared | 5/24/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 9/8/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/9/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 10/21/2021 | KURT CORRAL |
Contact Information
| Contractor | Ballard Nick Construction; Lic. No.: 1010094-B | 8017 CRENSHAW BLVD INGLEWOOD, CA 90305 |
| Engineer | Stewart,, Carl William; Lic. No.: C86681 | 8811 GENTLE WIND DR CORONA, CA 92883 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/21/2022 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 2/14/2022 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 2/17/2022 | Partial Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 2/24/2022 | Approved | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 4/15/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 5/5/2022 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 5/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/6/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 5/6/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 5/6/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/11/2022 | Approved | ANTHONY EGSON |
| Insulation | 5/20/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/20/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 6/3/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 7/22/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 7/22/2022 | Approved | ANTHONY EGSON |
| Sewer | 7/22/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 9/14/2022 | Corrections Issued | ANTHONY EGSON |
| Gas Test | 9/14/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 9/14/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 9/14/2022 | Approved | ANTHONY EGSON |
| Service/Power Release | 9/14/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 9/19/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/5/2022 | Approved | STUART CHAPMAN |
| Final | 10/5/2022 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/5/2022 | Approved | STUART CHAPMAN |
| Green Building Final | 10/5/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 10/5/2022 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 10/5/2022 | Approved | STUART CHAPMAN |
| Smoke Detectors | 10/5/2022 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 10/5/2022 | Approved | STUART CHAPMAN |
| Final | 10/7/2022 | OK to Issue CofO | ANTHONY EGSON |