5451 S BRYNHURST AVE 90043

Certificate Information: 5451 S BRYNHURST AVE 90043

Application / Permit
21010-10000-00264
Plan Check / Job No.
B21LA00923
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ADU AT REAR OF LOT PER LAMC 12.22 A 33 (c) AND (d)
Permit Issued
Issued on 11/22/2021
Issuing Office
Current Status
CofO Issued on 11/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2021 APPLICANT
Assigned to Plan Check Engineer 2/1/2021 RICARDO RAMIREZ
Corrections Issued 2/2/2021 RICARDO RAMIREZ
Plan Check Approved 10/27/2021 DANIEL SANJUAN
Issued 11/22/2021 APPLICANT
Building Plans Picked Up 11/24/2021 APPLICANT
CofO in Progress 10/7/2022 ANTHONY EGSON
Permit Finaled 11/5/2022 DEROLD HAUFF
Permit Finaled 11/5/2022 DEROLD HAUFF
CofO Issued 11/5/2022 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 5/5/2021 RIDWAN HARDY
Address approval Cleared 5/21/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/24/2021 JEANIE LAM
Sewer availability Cleared 5/24/2021 JEANIE LAM
Low Impact Development Cleared 9/8/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/9/2021 JEANIE LAM
Hydrant and Access approval Cleared 10/21/2021 KURT CORRAL

Contact Information

Contractor Ballard Nick Construction; Lic. No.: 1010094-B 8017 CRENSHAW BLVD      INGLEWOOD, CA 90305
Engineer Stewart,, Carl William; Lic. No.: C86681 8811 GENTLE WIND DR      CORONA, CA 92883

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/21/2022 Approved ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 2/14/2022 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 2/17/2022 Partial Approval ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 2/24/2022 Approved ANTHONY EGSON
Rough-Elec/Plmb/HVAC 4/15/2022 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 5/5/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 5/5/2022 Approved ANTHONY EGSON
Verify Sprinkler Sign Off 5/5/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 5/6/2022 Approved ANTHONY EGSON
HVAC-Rough 5/6/2022 Approved ANTHONY EGSON
PLUMBING-Rough 5/6/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 5/11/2022 Approved ANTHONY EGSON
Insulation 5/20/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 5/20/2022 Approved ANTHONY EGSON
Drywall Nailing 6/3/2022 Approved ANTHONY EGSON
ELECTRICAL-Rough 7/22/2022 Approved ANTHONY EGSON
PLUMBING-Rough 7/22/2022 Approved ANTHONY EGSON
Sewer 7/22/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 9/14/2022 Corrections Issued ANTHONY EGSON
Gas Test 9/14/2022 Approved ANTHONY EGSON
HVAC-Final 9/14/2022 Approved ANTHONY EGSON
PLUMBING-Final 9/14/2022 Approved ANTHONY EGSON
Service/Power Release 9/14/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 9/19/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 10/5/2022 Approved STUART CHAPMAN
Final 10/5/2022 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 10/5/2022 Approved STUART CHAPMAN
Green Building Final 10/5/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Approved STUART CHAPMAN
Service/Power Release 10/5/2022 Approved STUART CHAPMAN
Smoke Detectors 10/5/2022 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 10/5/2022 Approved STUART CHAPMAN
Final 10/7/2022 OK to Issue CofO ANTHONY EGSON