15625 W BLEDSOE ST 91342

Certificate Information: 15625 W BLEDSOE ST 91342

Application / Permit
21010-10000-00260
Plan Check / Job No.
B21LA00899
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(15) Public Utility Building
Work Description
(N) one-story, state-approved, pre-fabricated restroom building
Permit Issued
Issued on 9/3/2021
Issuing Office
Current Status
Issued on 9/3/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/28/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 ZAW HAN
Corrections Issued 2/8/2021 ZAW HAN
Disabled Access Plans Picked Up 2/16/2021 APPLICANT
Quality Review Completed 2/24/2021 GARO TELMI
Applicant returned to address corrections 8/9/2021 ZAW HAN
Plan Check Approved 8/10/2021 ZAW HAN
Issued 9/3/2021 APPLICANT
Building Plans Picked Up 9/9/2021 APPLICANT

Permit Application Clearance Information

Permit Cleared 3/22/2021 GABRIEL ROBLES
Sewer availability Cleared 3/22/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 3/23/2021 GABRIEL ROBLES
ZA Case Cleared 3/26/2021 DANIEL CORONADO
Certificate of Compliance Cleared 4/6/2021 DANIEL CORONADO
Comm Cor/Mini-Mall Cleared 4/6/2021 DANIEL CORONADO
Frnt yard landscape/Water mgmt Cleared 4/6/2021 DANIEL CORONADO
ZA Case Cleared 4/6/2021 DANIEL CORONADO
City owned building/parcel Cleared 5/5/2021 REVERDIA TRAMMELL
DAS Clearance Cleared 5/11/2021 ZAW HAN
Low Impact Development Cleared 5/18/2021 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 5/24/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 5/26/2021 BRIAN MILLER

Contact Information

Contractor California Landscape & Design Inc; Lic. No.: 597267-B 273 N BENSON AVE      UPLAND, CA 91786
Engineer Hume,, Thomas Wilfred; Lic. No.: C50647 PO BOX 15238      SAN LUIS OBISPO, CA 93406

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/21/2021 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 9/29/2021 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/30/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/1/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/25/2022 Approved DANNY RODRIGUEZ
Final 3/25/2022 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 3/25/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 3/25/2022 Approved DANNY RODRIGUEZ
Green Building Rough 3/25/2022 Approved DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/25/2022 SGSOV No Gas DANNY RODRIGUEZ
Smoke Detectors 3/25/2022 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/25/2022 Approved DANNY RODRIGUEZ
Wood Frame 3/25/2022 Approved DANNY RODRIGUEZ
Final 3/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Final 5/19/2022 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 5/19/2022 Not Ready for Inspection DANNY RODRIGUEZ
Final 12/22/2022 Partial Inspection DANNY RODRIGUEZ