3541 S MAY ST 90066

Certificate Information: 3541 S MAY ST 90066

Application / Permit
21010-10000-00256
Plan Check / Job No.
B21LA00876
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SFD WITH ATTACHED GARAGE
Permit Issued
Issued on 8/6/2021
Issuing Office
Current Status
CofO Issued on 7/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 STARR CHEN
Corrections Issued 1/31/2021 STARR CHEN
Quality Review Completed 2/11/2021 ALLEN MANALANSAN
Applicant returned to address corrections 3/5/2021 STARR CHEN
Applicant returned to address corrections 7/8/2021 STARR CHEN
Plan Check Approved 7/22/2021 STARR CHEN
Issued 8/6/2021 APPLICANT
Building Plans Picked Up 8/9/2021 APPLICANT
CofO in Progress 7/19/2022 RICHARD STEINBACH
Permit Finaled 7/21/2022 DANIEL ORRANTE
CofO Issued 7/21/2022 DANIEL ORRANTE
Permit Finaled 7/21/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/1/2021 ANTHONY MAINEZ
Permit Cleared 3/1/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 3/2/2021 ANTHONY MAINEZ
Sewer availability Cleared 3/2/2021 ANTHONY MAINEZ
Specific Plan Cleared 3/11/2021 FREDDY GARCIA
Trees in Parkway Cleared 3/17/2021 JOHN KIM
Hydrant and Access approval Cleared 5/1/2021 JOHN CONNEALLY
Low Impact Development Cleared 6/22/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/24/2021 DINAH GARIN
GPI Written Notices Cleared 7/8/2021 STARR CHEN
Grading Pre-Inspection Cleared 7/8/2021 STARR CHEN

Contact Information

Contractor Socal Construction Management Inc; Lic. No.: 984621-B 2129 S BURNSIDE AVENUE      LOS ANGELES, CA 90016
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/10/2021 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 9/13/2021 Approved WILLIAM MICHALAK
Footing/Foundation/Slab 9/13/2021 Approved WILLIAM MICHALAK
Deputy Wood Construction 10/1/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Conditional Approval RICHARD STEINBACH
Deputy Wood Construction 10/28/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Approved ENRIQUE MIRELES
HVAC-Rough 11/19/2021 Not Ready for Inspection ENRIQUE MIRELES
Sewer 11/19/2021 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 11/19/2021 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 11/19/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/30/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 11/30/2021 Corrections Issued DAVID FEILER
Green Building Rough 11/30/2021 Not Ready for Inspection DAVID FEILER
HVAC-Rough 11/30/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 11/30/2021 Approved DAVID FEILER
Verify Sprinkler Sign Off 11/30/2021 Approved DAVID FEILER
ELECTRICAL-Rough 12/2/2021 Approved ENRIQUE MIRELES
HVAC-Rough 12/2/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 12/2/2021 Approved ENRIQUE MIRELES
Shower Pan 12/2/2021 Approved ENRIQUE MIRELES
Wood Frame 12/2/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/3/2021 Approved ENRIQUE MIRELES
Green Building Rough 12/3/2021 Approved ENRIQUE MIRELES
Wood Frame 12/3/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 12/8/2021 Approved JOHN KAYON
Insulation 12/14/2021 Approved JOHN KAYON
Drywall Nailing 12/29/2021 Approved ENRIQUE MIRELES
Underground Mechanical 4/5/2022 Corrections Issued STEPHANIE SWANSON
Underground Mechanical 4/7/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 6/21/2022 Approved EVAN COOPER
Final 6/30/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Final 6/30/2022 Corrections Issued PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Not Ready PATRICK QUALEY
Service/Power Release 6/30/2022 Not Ready for Inspection PATRICK QUALEY
PLUMBING-Final 7/8/2022 Approved PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 7/8/2022 SGSOV Approved PATRICK QUALEY
Service/Power Release 7/8/2022 Not Ready for Inspection PATRICK QUALEY
Final 7/13/2022 Conditional Approval PATRICK QUALEY
Green Building Final 7/13/2022 Approved PATRICK QUALEY
HVAC-Final 7/13/2022 Approved PATRICK QUALEY
Service/Power Release 7/13/2022 Approved PATRICK QUALEY
Smoke Detectors 7/13/2022 Approved PATRICK QUALEY