1351 E 41ST ST BLDG 1 90011

Certificate Information: 1351 E 41ST ST BLDG 1 90011

Application / Permit
21010-10000-00248
Plan Check / Job No.
B21LA00798
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3 STORY TYPE VA 64 UNITS (4 ELI + 8VLI + 52 LI) 100% AFFORDABLE HOUSING APARTMENT, PER MEASURE JJJ
Permit Issued
Issued on 8/1/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 8/1/2022 MANUEL MONTUFAR
Issued 8/1/2022 APPLICANT
TCO Issued (Expire Date: 03-09-2025) 9/10/2024 ERNESTO CORRAL
CofO in Progress 3/7/2025 ERNESTO CORRAL
Permit Finaled 3/7/2025 ERNESTO CORRAL
CofO Issued 3/7/2025 ERNESTO CORRAL
Permit Finaled 3/7/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 5/26/2021 JEANIE LAM
Community Plan Implem. Overlay Cleared 5/26/2021 JEANIE LAM
Community Plan Implem. Overlay Cleared 10/13/2021 MOHAMMAD HASAN
Eng Process Fee Ord 176,300 Cleared 10/18/2021 JEANIE LAM
Highway dedication Cleared 10/18/2021 JEANIE LAM
Community Plan Implem. Overlay Cleared 10/29/2021 TORI CHEN
Trees in Parkway Cleared 12/8/2021 ADALBERTO VERA
Sewer availability Cleared 12/14/2021 JEANIE LAM
Permit Cleared 1/19/2022 MATIAS FARFAN
Community Plan Implem. Overlay Cleared 1/25/2022 ADALBERTO VERA
Building over 36-ft Cleared 3/1/2022 CALOSHA APPROVED
Encroachment in public way Cleared 3/17/2022 MSTAFA AL-MSARI
Green Code Cleared 4/6/2022 MANUEL MONTUFAR
Low Impact Development Cleared 4/19/2022 JORGE MEJIA LEMUS
Work Adjacent to Public Way Cleared 4/21/2022 ARMEN SARKISIAN
Hydrant and Access approval Cleared 4/22/2022 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 4/26/2022 AMAAN MALIK
Fire Marshal Fire Life Safety Cleared 5/11/2022 WILLIAM JOHNS
DCP conditions approval Cleared 6/2/2022 JAMES MCCARTHY
Density Bonus 12.22.A.31 Cleared 6/2/2022 JAMES MCCARTHY
Historic Resource Verification Cleared 6/21/2022 MAX LODER
Public Housing Cleared 6/30/2022 JOEL LAUNCHBAUGH
"Q" conditions Cleared 7/11/2022 RUBEN VASQUEZ
"T" removal Cleared 7/11/2022 RUBEN VASQUEZ
CPC Cleared 7/11/2022 RUBEN VASQUEZ
Community Plan Implem. Overlay Cleared 7/11/2022 RUBEN VASQUEZ
Frnt yard landscape/Water mgmt Cleared 7/11/2022 RUBEN VASQUEZ
Miscellaneous Cleared 7/11/2022 RUBEN VASQUEZ
Miscellaneous Cleared 7/11/2022 RUBEN VASQUEZ
Miscellaneous Cleared 7/11/2022 RUBEN VASQUEZ
Opn space landscape/Water mgmt Cleared 7/11/2022 RUBEN VASQUEZ
Prkng lot landscape/Water mgmt Cleared 7/11/2022 RUBEN VASQUEZ
Redevelopment Project Area Cleared 7/14/2022 SUSAN WONG
DAS Clearance Cleared 8/1/2022 ELIZABETH TOMS

Contact Information

Architect Withee,, Dan Richard; Lic. No.: C9049 2251 W 190TH STREET      TORRANCE, CA 90504
Contractor Lena Construction Inc; Lic. No.: 1073212-B 1112 S SAN JULIAN ST      LOS ANGELES, CA 90015
Engineer Cunningham,, William Charbern; Lic. No.: C80129 2745 PARKVIEW DRIVE      THOUSAND OAKS, CA 91362
Engineer Hassan,, Mohamed Ali; Lic. No.: S5285 3621 HARBOR BLVD #125      SANTA ANA, CA 92704
Geologist Feffer,, Joshua R; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049
Landscape Architect Jackson,, Matthew; Lic. No.: LA4403 511 30TH STREET      NEWPORT BEACH, CA 92663

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/28/2022 Approved JAMES POWERS
Grading Pre-Inspection 10/12/2022 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 12/6/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/20/2022 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 12/21/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/28/2022 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 12/29/2022 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 12/30/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/30/2022 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 12/30/2022 Corrections Issued DARRYL ARNOLD
Deputy Reinf. Concrete 1/25/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/26/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/27/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 1/27/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/28/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/30/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/30/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/31/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/8/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/10/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/16/2023 Conditional Approval ALAN MORELOS
Deputy Reinf. Concrete 2/17/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 3/8/2023 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/24/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 4/3/2023 Not Ready for Inspection GREGORY POMISH
Deputy Drilled-In Anchors 4/4/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/4/2023 Partial Approval JAMES POWERS
Deputy Fireproofing 4/7/2023 Partial Approval JAMES POWERS
Deputy Fireproofing 4/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 4/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 4/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 4/14/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 4/14/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 4/14/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 4/19/2023 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 4/19/2023 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 4/27/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 5/8/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Partial Approval JAMES POWERS
Green Building Rough 5/8/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 5/8/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 5/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 5/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 5/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 5/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/11/2023 Conditional Approval LARRY ARNICK
Deputy Wood Construction 5/11/2023 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 5/12/2023 Partial Approval LARRY ARNICK
Deputy Wood Construction 5/12/2023 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 5/16/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 5/18/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 5/22/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 5/24/2023 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 5/26/2023 Conditional Approval LARRY ARNICK
Drywall Nailing 5/26/2023 Not Ready for Inspection LARRY ARNICK
Deputy Fireproofing 6/7/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Partial Approval JAMES POWERS
Insulation 6/7/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/7/2023 Not Ready for Inspection JAMES POWERS
Drywall Nailing 6/8/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/12/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 6/12/2023 Partial Approval JAMES POWERS
Drywall Nailing 6/15/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/23/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/23/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 6/23/2023 Partial Approval JAMES POWERS
Deputy Fireproofing 6/26/2023 Partial Approval JAMES POWERS
Deputy Fireproofing 6/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 6/28/2023 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Partial Approval RAFAEL CORTES
Deputy Fireproofing 7/11/2023 Partial Approval JAMES POWERS
Insulation 7/11/2023 Partial Approval JAMES POWERS
Deputy Fireproofing 7/12/2023 Partial Approval JAMES POWERS
Deputy Fireproofing 7/13/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/24/2023 Corrections Issued DARRYL ARNOLD
Insulation 7/25/2023 Partial Approval JAMES POWERS
Insulation 8/4/2023 Corrections Issued LARRY ARNICK
Deputy Wood Construction 8/7/2023 Partial Approval JAMES POWERS
Drywall Nailing 8/7/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 8/8/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 8/9/2023 Partial Approval JAMES POWERS
Drywall Nailing 8/9/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 8/10/2023 Partial Approval JAMES POWERS
Drywall Nailing 8/10/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 8/11/2023 Partial Approval JAMES POWERS
Insulation 8/14/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 8/15/2023 Partial Approval JAMES POWERS
Insulation 8/15/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 8/16/2023 Conditional Approval ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 8/16/2023 Partial Approval ALAN MORELOS
Deputy Wood Construction 8/17/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 8/18/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Partial Approval JAMES POWERS
Insulation 8/18/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 8/29/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 8/30/2023 Partial Approval JAMES POWERS
Insulation 8/30/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 8/31/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 9/1/2023 Partial Approval JAMES POWERS
Drywall Nailing 9/5/2023 Partial Approval JAMES POWERS
Insulation 9/5/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 9/12/2023 Partial Approval JAMES POWERS
Drywall Nailing 9/12/2023 Not Ready for Inspection JAMES POWERS
Insulation 9/12/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 9/13/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 9/19/2023 Partial Approval JAMES POWERS
Drywall Nailing 9/19/2023 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 9/20/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 9/21/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 9/22/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 9/26/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 9/27/2023 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 9/27/2023 Partial Approval RAFAEL ESPINOZA
Insulation 9/27/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/2/2023 Partial Approval JAMES POWERS
Insulation 10/2/2023 Partial Approval JAMES POWERS
Drywall Nailing 10/4/2023 Partial Approval RAFAEL ESPINOZA
Insulation 10/4/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/10/2023 Partial Approval JAMES POWERS
Drywall Nailing 10/11/2023 Partial Approval JAMES POWERS
Drywall Nailing 10/16/2023 Partial Approval JAMES POWERS
Insulation 10/16/2023 Not Ready for Inspection JAMES POWERS
Drywall Nailing 10/20/2023 Partial Approval LARRY ARNICK
Insulation 10/23/2023 Partial Approval GREGORY POMISH
Drywall Nailing 10/27/2023 Not Ready for Inspection LARRY ARNICK
Insulation 10/27/2023 Partial Approval LARRY ARNICK
Drywall Nailing 11/1/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 11/1/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 11/1/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 11/6/2023 Partial Inspection RAFAEL ESPINOZA
Wood Frame 11/6/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/7/2023 Partial Approval JAMES POWERS
Insulation 11/8/2023 Partial Approval JAMES POWERS
Drywall Nailing 11/9/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/9/2023 Not Ready for Inspection JAMES POWERS
Insulation 11/9/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 11/15/2023 Partial Approval JAMES POWERS
Drywall Nailing 11/15/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Not Ready for Inspection JAMES POWERS
Insulation 11/15/2023 Partial Approval JAMES POWERS
Drywall Nailing 11/17/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Not Ready for Inspection JAMES POWERS
Insulation 11/17/2023 Partial Approval JAMES POWERS
Drywall Nailing 11/27/2023 Partial Approval JAMES POWERS
Insulation 11/27/2023 Partial Approval JAMES POWERS
Insulation 12/4/2023 Partial Approval JAMES POWERS
Drywall Nailing 12/6/2023 Not Ready for Inspection LARRY ARNICK
Insulation 12/6/2023 Partial Approval LARRY ARNICK
Drywall Nailing 12/12/2023 Partial Approval LARRY ARNICK
Insulation 12/12/2023 Partial Approval LARRY ARNICK
Drywall Nailing 12/13/2023 Partial Approval LARRY ARNICK
Insulation 12/13/2023 Partial Approval LARRY ARNICK
Drywall Nailing 12/14/2023 Partial Approval LARRY ARNICK
Insulation 12/14/2023 Partial Approval LARRY ARNICK
Drywall Nailing 12/19/2023 Not Ready for Inspection JAMES POWERS
Insulation 12/19/2023 Partial Approval JAMES POWERS
Drywall Nailing 12/20/2023 Partial Approval JAMES POWERS
Insulation 12/20/2023 Partial Approval JAMES POWERS
Insulation 12/22/2023 Partial Approval JAMES POWERS
Insulation 12/26/2023 Partial Approval JAMES POWERS
Drywall Nailing 12/27/2023 Partial Approval JAMES POWERS
Insulation 12/27/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 12/28/2023 Partial Approval JAMES POWERS
Drywall Nailing 12/28/2023 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 12/28/2023 Partial Approval JAMES POWERS
Drywall Nailing 12/29/2023 Partial Approval JAMES POWERS
Insulation 12/29/2023 Not Ready for Inspection JAMES POWERS
Drywall Nailing 1/5/2024 Not Ready for Inspection JAMES POWERS
Insulation 1/5/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 1/8/2024 Not Ready for Inspection LARRY ARNICK
Insulation 1/8/2024 Partial Approval LARRY ARNICK
Deputy Steel/Welding 1/11/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 1/11/2024 Partial Approval JAMES POWERS
Insulation 1/11/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 1/12/2024 Partial Approval JAMES POWERS
Insulation 1/16/2024 Partial Approval JAMES POWERS
Drywall Nailing 1/17/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/18/2024 Not Ready for Inspection JAMES POWERS
Insulation 2/2/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 2/14/2024 Partial Approval JAMES POWERS
Drywall Nailing 2/15/2024 Partial Approval JAMES POWERS
Insulation 2/15/2024 Partial Approval JAMES POWERS
Drywall Nailing 2/22/2024 Partial Approval JAMES POWERS
Insulation 2/22/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/22/2024 Not Ready for Inspection JAMES POWERS
Insulation 4/5/2024 Partial Approval JAMES POWERS
Drywall Nailing 4/10/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/10/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 4/12/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/12/2024 Partial Approval JAMES POWERS
Masonry Wall/Backfill 4/12/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 4/16/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/26/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/2/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/13/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/15/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/23/2024 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 5/31/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 6/3/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/5/2024 Partial Approval JAMES POWERS
Masonry Wall/Backfill 6/5/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/7/2024 Partial Approval JAMES POWERS
Final 6/10/2024 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 6/10/2024 Approved JAMES POWERS
Green Building Final 6/10/2024 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 6/10/2024 SGSOV Not Ready JAMES POWERS
Smoke Detectors 6/10/2024 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 6/10/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 6/10/2024 Partial Approval JAMES POWERS
Masonry Wall/Backfill 6/14/2024 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 6/14/2024 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 6/17/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/5/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/19/2024 Partial Approval JAMES POWERS
Pre-Inspection 8/1/2024 Partial Approval JAMES POWERS
Special/Order Compliance 8/15/2024 Partial Approval JAMES POWERS
Final 8/21/2024 Not Ready for Inspection JAMES POWERS
Green Building Final 8/21/2024 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 8/21/2024 SGSOV Not Ready JAMES POWERS
Smoke Detectors 8/21/2024 Approved JAMES POWERS
Verify Sprinkler Sign Off 8/21/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 8/21/2024 Partial Approval JAMES POWERS
Final 8/26/2024 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 8/26/2024 SGSOV Not Required JAMES POWERS
Verify Sprinkler Sign Off 8/26/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 8/26/2024 Partial Approval JAMES POWERS
Special/Order Compliance 8/27/2024 Partial Approval JAMES POWERS
Final 9/5/2024 Not Ready for Inspection RONALD JIMENEZ
Verify Sprinkler Sign Off 9/5/2024 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 9/5/2024 Not Ready for Inspection RONALD JIMENEZ
Final 9/9/2024 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 9/9/2024 Partial Approval JAMES POWERS
Wood Frame 9/9/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/25/2024 Partial Approval JAMES POWERS
Special/Order Compliance 2/11/2025 Partial Approval JAMES POWERS
Final 3/7/2025 OK to Issue CofO ERNESTO CORRAL
Verify Sprinkler Sign Off 3/7/2025 Approved ERNESTO CORRAL
Wood Frame 3/7/2025 Approved ERNESTO CORRAL