Work Description
**eplan adu conversion** CONVERT EXISTING DETACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(A) PER WFPP "COMPLY WITH DEPARTMENT ORDER effective date 11/05/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 4/27/2023
Issuing Office
Current Status
CofO Issued on 3/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 CRYSTEL MAALOUF
Corrections Issued 2/17/2021 CRYSTEL MAALOUF
Quality Review Completed 2/26/2021 HERNAN ARREOLA
Applicant returned to address corrections 3/19/2021 CRYSTEL MAALOUF
Plan Check Approved 4/6/2021 CRYSTEL MAALOUF
Plan Check Approved 1/26/2023 CRYSTEL MAALOUF
Issued 4/27/2023 APPLICANT
CofO in Progress 3/14/2025 WILLIAM MICHALAK
Permit Finaled 3/27/2025 CLAUDIO MORENO
Permit Finaled 3/27/2025 CLAUDIO MORENO
CofO Issued 3/27/2025 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 3/12/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 3/12/2021 ROSA SILVA
Sewer availability Cleared 3/12/2021 ROSA SILVA
HPOZ Cleared 3/18/2021 MAX LODER
ZI Cleared 3/18/2021 MAX LODER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/20/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 5/20/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 5/20/2024 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Final 5/20/2024 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Rough 5/20/2024 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 5/20/2024 Not Ready for Inspection WILLIAM MICHALAK
Final 5/23/2024 Corrections Issued WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 6/28/2024 SGSOV Not Ready ENRIQUE PREZA
BUILDING-Rough-Frame 7/8/2024 Not Ready for Inspection WILLIAM MICHALAK
Final 7/8/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 7/8/2024 Corrections Issued WILLIAM MICHALAK
Green Building Rough 7/8/2024 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Final 7/8/2024 Approved WILLIAM MICHALAK
METHANE-Rough 7/8/2024 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 7/8/2024 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 7/8/2024 Partial Approval WILLIAM MICHALAK
Excavation/Setback/Form/Re-Bar 7/24/2024 Approved WILLIAM MICHALAK
PLUMBING-Rough 8/8/2024 Corrections Issued WILLIAM MICHALAK
BUILDING-Rough-Frame 8/13/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 8/13/2024 Not Ready for Inspection WILLIAM MICHALAK
Interior/Exterior Lathing 9/9/2024 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Not Ready WILLIAM MICHALAK
BUILDING-Rough-Frame 12/9/2024 Corrections Issued WILLIAM MICHALAK
Final 12/9/2024 No Access for Inspection WILLIAM MICHALAK
Green Building Final 12/9/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 12/9/2024 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 12/9/2024 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 12/9/2024 Approved WILLIAM MICHALAK
ELECTRICAL-Final 1/17/2025 Corrections Issued WILLIAM MICHALAK
PLUMBING-Final 1/17/2025 Corrections Issued WILLIAM MICHALAK
BUILDING-Rough-Frame 1/31/2025 Corrections Issued WILLIAM MICHALAK
Final 1/31/2025 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 1/31/2025 Corrections Issued WILLIAM MICHALAK
Green Building Rough 1/31/2025 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 1/31/2025 SGSOV Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 3/14/2025 Approved WILLIAM MICHALAK
Final 3/14/2025 OK to Issue CofO WILLIAM MICHALAK
Green Building Final 3/14/2025 Approved WILLIAM MICHALAK
Green Building Rough 3/14/2025 Approved WILLIAM MICHALAK