13030 W WARREN AVE 90066

Certificate Information: 13030 W WARREN AVE 90066

Application / Permit
21010-10000-00228
Plan Check / Job No.
B21LA00741
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
Permit Issued
Issued on 7/30/2021
Issuing Office
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 KEVIN MORALES
Corrections Issued 1/27/2021 KEVIN MORALES
Quality Review Completed 1/28/2021 EUGENE BARBEAU
Building Plans Picked Up 2/1/2021 APPLICANT
Plan Check Approved 7/30/2021 KEVIN MORALES
Issued 7/30/2021 APPLICANT
CofO in Progress 12/9/2022 EVAN COOPER
No Progress 12/16/2022 RICHARD STEINBACH
CofO in Progress 12/16/2022 RICHARD STEINBACH
Permit Finaled 12/17/2022 DANIEL ORRANTE
CofO Issued 12/17/2022 DANIEL ORRANTE
Permit Finaled 12/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/4/2021 MATTHEW CRAIG
Address approval Cleared 5/26/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 5/26/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 5/26/2021 HISASHI KOBAYAKAWA
Specific Plan Cleared 5/26/2021 KEVIN ARUCAN
Low Impact Development Cleared 7/8/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/13/2021 HISASHI KOBAYAKAWA
GPI Written Notices Cleared 7/30/2021 KEVIN MORALES
Grading Pre-Inspection Cleared 7/30/2021 KEVIN MORALES

Contact Information

Architect Rezvani,, Farbod; Lic. No.: C32315 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Contractor Di Nalli Construction; Lic. No.: 942979-B 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Engineer Askarian,, Soroosh Namaghi; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/31/2021 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 9/1/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 9/1/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 9/8/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/12/2021 Partial Approval ENRIQUE MIRELES
Deputy Steel/Welding 11/12/2021 Approved ENRIQUE MIRELES
Green Building Rough 11/12/2021 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 11/12/2021 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/9/2021 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/14/2021 Partial Approval DAVID FEILER
Deputy Wood Construction 1/7/2022 Conditional Approval RICHARD STEINBACH
ELECTRICAL-Rough 1/11/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/11/2022 Approved ENRIQUE MIRELES
HVAC-Rough 1/11/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/11/2022 Approved ENRIQUE MIRELES
Green Building Rough 1/19/2022 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 1/19/2022 Approved ENRIQUE MIRELES
Wood Frame 1/21/2022 Partial Approval DEANDRE HOFFMAN
Interior/Exterior Lathing 1/27/2022 Approved ENRIQUE MIRELES
Insulation 1/28/2022 Approved ENRIQUE MIRELES
Drywall Nailing 2/4/2022 Approved KRISTEN CAUSEY
Shower Pan 2/4/2022 Approved KRISTEN CAUSEY
Deputy Shotcrete 2/7/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/14/2022 Approved STEPHANIE SWANSON
Special/Order Compliance 7/18/2022 Partial Inspection PATRICK QUALEY
Pre-Inspection 7/22/2022 Partial Inspection DAVID FEILER
Special/Order Compliance 7/22/2022 Partial Inspection RICHARD STEINBACH
ELECTRICAL-Final 8/31/2022 Corrections Issued DAVID FEILER
HVAC-Final 8/31/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Final 8/31/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Final 9/2/2022 Not Ready for Inspection DAVID FEILER
Gas Test 9/2/2022 Approved DAVID FEILER
HVAC-Final 9/2/2022 Corrections Issued DAVID FEILER
PLUMBING-Final 9/2/2022 Approved DAVID FEILER
ELECTRICAL-Final 9/7/2022 Approved DAVID FEILER
HVAC-Final 9/7/2022 Not Ready for Inspection DAVID FEILER
HVAC-Final 9/15/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/23/2022 Approved DAVID FEILER
Final 11/23/2022 Corrections Issued DAVID FEILER
Green Building Final 11/23/2022 Corrections Issued DAVID FEILER
SGSOV-Seismic Gas S/O Valve 11/23/2022 SGSOV Approved DAVID FEILER
Service/Power Release 11/23/2022 Not Ready for Inspection DAVID FEILER
Smoke Detectors 11/23/2022 Approved DAVID FEILER
Final 12/6/2022 Corrections Issued EVAN COOPER
Green Building Final 12/6/2022 Approved EVAN COOPER
Service/Power Release 12/6/2022 Approved EVAN COOPER
Special/Order Compliance 12/6/2022 Partial Inspection JEREMY TODD
Final 12/8/2022 OK to Issue CofO EVAN COOPER