4013-4015 S DALTON AVE 90062
Certificate Information: 4013-4015 S DALTON AVE 90062
- Application / Permit
- 21010-10000-00194
- Plan Check / Job No.
- B21LA00599
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX W/ TWO CAR ATTACHED GARAGE BUILDING PER ENGINEER DESIGN (NFPA 13D THRU OUT)
- Permit Issued
- Issued on 10/17/2024
- Issuing Office
- Current Status
- CofO Issued on 7/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2021 | AUNG SOE |
| Corrections Issued | 4/23/2021 | AUNG SOE |
| Quality Review Completed | 4/27/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 5/4/2021 | APPLICANT |
| Applicant returned to address corrections | 10/15/2024 | AUNG SOE |
| Plan Check Approved | 10/17/2024 | AUNG SOE |
| Issued | 10/17/2024 | APPLICANT |
| CofO in Progress | 7/25/2025 | SABAS ALONSO |
| Permit Finaled | 7/27/2025 | DEROLD HAUFF |
| CofO Issued | 7/27/2025 | DEROLD HAUFF |
| Permit Finaled | 7/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/7/2021 | WALLIE JONG |
| Highway dedication | Cleared | 5/21/2024 | JEANIE LAM |
| Permit | Cleared | 5/21/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2024 | WALLIE JONG |
| Sewer availability | Cleared | 6/5/2024 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 6/13/2024 | RICARDO BOHORQUEZ |
| Trees in Parkway | Cleared | 7/8/2024 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 8/15/2024 | KURT CORRAL |
| Low Impact Development | Cleared | 8/26/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 8/27/2024 | DAVID LOPEZ |
Contact Information
| Architect | Feagins,, Larry; Lic. No.: C27009 | 669 N THIRD AVENUE UPLAND, CA 91786 |
| Contractor | R & M Real Estate Investments And Renovators Inc; Lic. No.: 1075969-B | 10910 LONG BEACH BLVD STE 103 LYNWOOD, CA 902622683 |
| Engineer | Lee,, Allen; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/28/2024 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 10/31/2024 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 1/15/2025 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 1/15/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 1/24/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 2/4/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 2/4/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 2/4/2025 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 2/4/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/5/2025 | Approved | SABAS ALONSO |
| Insulation | 2/10/2025 | Approved | SABAS ALONSO |
| Sewer | 2/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 2/20/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 2/20/2025 | Approved | SABAS ALONSO |
| Sewer | 2/20/2025 | Approved | SABAS ALONSO |
| Shower Pan | 2/20/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 6/2/2025 | Partial Approval | MICHAEL LEWIS |
| HVAC-Final | 6/2/2025 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 6/2/2025 | Approved | MICHAEL LEWIS |
| HVAC-Final | 6/6/2025 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 6/18/2025 | No Access for Inspection | SABAS ALONSO |
| Final | 6/23/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 6/23/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/23/2025 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 6/23/2025 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 6/26/2025 | Approved | SABAS ALONSO |
| Service/Power Release | 6/26/2025 | Approved | SABAS ALONSO |
| Smoke Detectors | 6/26/2025 | Approved | SABAS ALONSO |
| Final | 7/15/2025 | Corrections Issued | SABAS ALONSO |
| Final | 7/25/2025 | OK to Issue CofO | SABAS ALONSO |