214-214 1/2 E 24TH ST 90011

Certificate Information: 214-214 1/2 E 24TH ST 90011

Application / Permit
21010-10000-00156
Plan Check / Job No.
B21LA00440
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-STORY 39'X35' DUPLEX 2625.0 SF (REAR BLDG.). 2 OF 2 "COMPLY WITH DEPARTMENT ORDER effective date 03/22/2016. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 8/24/2021
Issuing Office
Current Status
CofO Issued on 3/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 CHUNG-WEN CHUANG
Corrections Issued 3/2/2021 CHUNG-WEN CHUANG
Quality Review Completed 3/3/2021 JASON HEALEY
Applicant returned to address corrections 6/10/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 7/21/2021 CHUNG-WEN CHUANG
Plan Check Approved 7/22/2021 CHUNG-WEN CHUANG
Issued 8/24/2021 APPLICANT
Building Plans Picked Up 8/26/2021 APPLICANT
CofO in Progress 3/29/2023 BRENDAN MORELLI
Permit Finaled 3/30/2023 DEROLD HAUFF
CofO Issued 3/30/2023 DEROLD HAUFF
Permit Finaled 3/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/8/2021 CELINA MORENO
Permit Cleared 3/8/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/22/2021 CELINA MORENO
Sewer availability Cleared 3/22/2021 CELINA MORENO
Trees in Parkway Cleared 4/26/2021 JOHN KIM
Hydrant and Access approval Cleared 5/28/2021 JOHN CONNEALLY
Low Impact Development Cleared 6/2/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/3/2021 THAN WIN

Contact Information

Contractor New World Construction; Lic. No.: 864461-B 838 E 93RD STREET      LOS ANGELES, CA 90002
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/13/2021 Partial Approval WILLIAM WREN
PLUMBING-Rough 9/13/2021 Approved WILLIAM WREN
Underground Mechanical 9/13/2021 Approved WILLIAM WREN
Excavation/Setback/Form/Re-Bar 9/21/2021 No Access for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 No Access for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 12/3/2021 Not Ready for Inspection SABAS ALONSO
METHANE-Barrier 12/3/2021 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 12/3/2021 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/15/2021 Conditional Approval SABAS ALONSO
METHANE-Rough 3/30/2022 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/4/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 4/4/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 4/4/2022 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 4/4/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 4/4/2022 Corrections Issued JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 4/4/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 4/12/2022 Conditional Approval JOAQUIN GREENOUGH
PLUMBING-Rough 4/12/2022 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/22/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 4/22/2022 Approved JOAQUIN GREENOUGH
Green Building Rough 4/22/2022 Approved JOAQUIN GREENOUGH
METHANE-Rough 4/22/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 4/22/2022 Approved JOAQUIN GREENOUGH
Insulation 5/5/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 5/5/2022 Approved HORACE FULTZ
Drywall Nailing 6/1/2022 Corrections Issued LILIANA PORTILLO
Special/Order Compliance 6/7/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Drywall Nailing 6/14/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 2/17/2023 Approved BRENDAN MORELLI
HVAC-Final 2/17/2023 Approved BRENDAN MORELLI
Service/Power Release 2/17/2023 Approved BRENDAN MORELLI
Final 3/13/2023 OK to Issue CofO BRENDAN MORELLI
Footing/Foundation/Slab 3/13/2023 Approved BRENDAN MORELLI
Green Building Final 3/13/2023 Approved BRENDAN MORELLI
METHANE-Barrier 3/13/2023 Approved BRENDAN MORELLI
METHANE-Subgrade 3/13/2023 Approved BRENDAN MORELLI
PLUMBING-Final 3/13/2023 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 3/13/2023 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 3/13/2023 Approved BRENDAN MORELLI