15057 1/2 W PADDOCK ST 91342

Certificate Information: 15057 1/2 W PADDOCK ST 91342

Application / Permit
21010-10000-00143
Plan Check / Job No.
B21LA00400
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**eplan** New detached ADU 25'x36'. WFPP.
Permit Issued
Issued on 3/9/2022
Issuing Office
Current Status
CofO Issued on 9/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 CRYSTEL MAALOUF
Corrections Issued 2/17/2021 CRYSTEL MAALOUF
Quality Review Completed 2/26/2021 HERNAN ARREOLA
Plan Check Approved 3/9/2022 CRYSTEL MAALOUF
Issued 3/9/2022 APPLICANT
CofO in Progress 6/24/2022 JENNIFER RABUCHIN
Permit Finaled 9/13/2022 MICHAEL SMITH
CofO Issued 9/13/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/29/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/30/2021 GABRIEL ROBLES
Sewer availability Cleared 6/30/2021 GABRIEL ROBLES
Construction near power lines Cleared 9/30/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 2/8/2022 KURT CORRAL
Grading Pre-Inspection Cleared 2/17/2022 SERGIO VALENZUELA
Low Impact Development Cleared 3/8/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 3/8/2022 MARKOS PEREZ-BRAN
GPI Written Notices Cleared 3/9/2022 CRYSTEL MAALOUF

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/15/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 3/15/2022 Partial Approval JENNIFER RABUCHIN
Sewer 3/15/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/29/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 3/29/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Approved JENNIFER RABUCHIN
Gas Test 3/29/2022 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 3/29/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/29/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/1/2022 Partial Approval JENNIFER RABUCHIN
Gas Test 4/1/2022 Partial Approval JENNIFER RABUCHIN
Green Building Rough 4/1/2022 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 4/1/2022 Partial Approval JENNIFER RABUCHIN
Insulation 4/7/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 4/11/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 4/11/2022 Approved DEANDRE HOFFMAN
Shower Pan 4/11/2022 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 5/23/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/23/2022 Corrections Issued JENNIFER RABUCHIN
Final 5/23/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 5/23/2022 Approved JENNIFER RABUCHIN
Green Building Final 5/23/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 5/23/2022 Approved JENNIFER RABUCHIN
HVAC-Final 5/23/2022 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/23/2022 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 5/23/2022 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 5/23/2022 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 5/23/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/15/2022 Approved JENNIFER RABUCHIN
Final 6/15/2022 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 6/15/2022 Approved JENNIFER RABUCHIN
HVAC-Final 6/15/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 6/15/2022 Approved JENNIFER RABUCHIN
Service/Power Release 6/15/2022 Approved JENNIFER RABUCHIN