4948 N GLORIA AVE 91436
Certificate Information: 4948 N GLORIA AVE 91436
- Application / Permit
- 21010-10000-00142
- Plan Check / Job No.
- B21LA00399
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** PROPOSED ONE STORY DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE. ***SHALL BE SPRINKLERED PER NFPA 13D***
- Permit Issued
- Issued on 7/1/2022
- Issuing Office
- Current Status
- CofO Issued on 1/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | MICHAEL LOPEZ |
| Corrections Issued | 2/16/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 2/26/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/14/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 6/29/2022 | MICHAEL LOPEZ |
| Issued | 7/1/2022 | APPLICANT |
| CofO in Progress | 12/28/2023 | VINCENT HANLEY |
| Permit Finaled | 1/5/2024 | JOHN JANSON |
| CofO Issued | 1/5/2024 | JOHN JANSON |
| Permit Finaled | 1/5/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/19/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 2/18/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/30/2022 | JOHN LIN |
| Hydrant and Access approval | Cleared | 4/13/2022 | GREGORY HOERNER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2022 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/5/2023 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 5/5/2023 | Partial Approval | VINCENT HANLEY |
| Sewer | 5/5/2023 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/10/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/10/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/16/2023 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/16/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2023 | Partial Approval | VINCENT HANLEY |
| Gas Test | 6/16/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/16/2023 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 6/16/2023 | Approved | VINCENT HANLEY |
| Underground Mechanical | 6/16/2023 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 6/16/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Wood Frame | 6/16/2023 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/28/2023 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/28/2023 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 6/28/2023 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 6/28/2023 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 6/28/2023 | Corrections Issued | VINCENT HANLEY |
| Wood Frame | 6/28/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/10/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 7/10/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/10/2023 | Partial Approval | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 7/10/2023 | Approved | VINCENT HANLEY |
| Insulation | 7/18/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 7/21/2023 | Approved | VINCENT HANLEY |
| Drywall Nailing | 7/28/2023 | Approved | VINCENT HANLEY |
| Gas Test | 10/11/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 12/26/2023 | Approved | VINCENT HANLEY |
| Final | 12/26/2023 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 12/26/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 12/26/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 12/26/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/26/2023 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 12/26/2023 | Approved | VINCENT HANLEY |
| Smoke Detectors | 12/26/2023 | Approved | VINCENT HANLEY |