6833 N ALDEA AVE 91406
Certificate Information: 6833 N ALDEA AVE 91406
- Application / Permit
- 21010-10000-00139
- Plan Check / Job No.
- B21LA00388
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: NEW DETACHED ADU 745 SQ. FT
- Permit Issued
- Issued on 12/29/2021
- Issuing Office
- Current Status
- CofO Issued on 4/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 2/10/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/21/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/17/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 12/17/2021 | ARSALAN SHABESTARI |
| Issued | 12/29/2021 | APPLICANT |
| CofO in Progress | 11/3/2022 | SEAN HAUPT |
| No Progress | 12/23/2022 | MICHAEL SMITH |
| CofO in Progress | 4/13/2023 | MICHAEL SMITH |
| Permit Finaled | 4/13/2023 | MICHAEL SMITH |
| CofO Issued | 4/13/2023 | MICHAEL SMITH |
| Permit Finaled | 4/13/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/26/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/26/2021 | RIDWAN HARDY |
| Watercourse | Cleared | 4/13/2021 | LEE GUILBEAUX |
| Address approval | Cleared | 4/15/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/22/2021 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 5/21/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 10/15/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/19/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alson,, Ken; Lic. No.: NA41697 | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/10/2022 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 2/14/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/14/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2022 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 4/1/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 4/1/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 4/1/2022 | Approved | SEAN HAUPT |
| Insulation | 4/6/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 4/6/2022 | Approved | SEAN HAUPT |
| Shower Pan | 4/6/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 4/13/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 4/13/2022 | Approved | KRISTEN CAUSEY |
| Underground Mechanical | 6/9/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 11/2/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 11/2/2022 | Approved | SEAN HAUPT |
| Final | 11/2/2022 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 11/2/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 11/2/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 11/2/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 11/2/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 11/2/2022 | Approved | SEAN HAUPT |
| Smoke Detectors | 11/2/2022 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 11/2/2022 | Approved | SEAN HAUPT |