4808 1/2 S 8TH AVE 90043

Certificate Information: 4808 1/2 S 8TH AVE 90043

Application / Permit
21010-10000-00058
Plan Check / Job No.
B21LA00146
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER STATE LAW LAMC 12.22A.33(b)(6)
Permit Issued
Issued on 9/14/2021
Issuing Office
Current Status
Issued on 9/14/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/7/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 VU NGUYEN
Corrections Issued 2/2/2021 VU NGUYEN
Quality Review Completed 2/4/2021 EUGENE BARBEAU
Building Plans Picked Up 2/17/2021 APPLICANT
Applicant returned to address corrections 8/20/2021 VU NGUYEN
Plan Check Approved 9/13/2021 VU NGUYEN
Issued 9/14/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/2/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 3/12/2021 THOMAS LANG
Sewer availability Cleared 4/20/2021 THOMAS LANG
Low Impact Development Cleared 6/10/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/17/2021 THOMAS LANG
Construction near power lines Cleared 8/2/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/24/2023 Partial Inspection ANTHONY EGSON
Pre-Inspection 7/28/2023 Partial Inspection ANTHONY EGSON
Pre-Inspection 9/13/2024 Partial Inspection ANTHONY EGSON