4324 S ALLA ROAD 90066
Certificate Information: 4324 S ALLA ROAD 90066
- Application / Permit
- 21010-10000-00030
- Plan Check / Job No.
- B21LA00092
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- e-plan: New detached ADU (1-STORY) PER STATE LAW
- Permit Issued
- Issued on 11/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | CARLOS MONTES |
| Corrections Issued | 2/4/2021 | CARLOS MONTES |
| Quality Review Completed | 2/4/2021 | TU HUA |
| Applicant returned to address corrections | 4/7/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 4/30/2021 | CARLOS MONTES |
| Plan Check Approved | 5/5/2021 | CARLOS MONTES |
| Issued | 11/19/2021 | APPLICANT |
| CofO in Progress | 6/7/2022 | PATRICK QUALEY |
| CofO in Progress | 6/8/2022 | RICHARD STEINBACH |
| CofO in Progress | 8/25/2022 | JESUS RODRIGUEZ |
| Permit Finaled | 8/26/2022 | DANIEL ORRANTE |
| CofO Issued | 8/26/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/26/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/5/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 3/5/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2021 | DINAH GARIN |
| Sewer availability | Cleared | 3/8/2021 | DINAH GARIN |
| Specific Plan | Cleared | 3/15/2021 | VALERIA CEJA |
| Hydrant and Access approval | Cleared | 4/23/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Building Blocks Ca Llc; Lic. No.: 1034808-B | 180 SOUTH CITRUS AVENUE LOS ANGELES, CA 90036 |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | 1898 WILDROSE AVE POMONA, CA 91767 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/7/2021 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 1/7/2022 | Not Ready for Inspection | DAVID FEILER |
| Sewer | 1/7/2022 | Not Ready for Inspection | DAVID FEILER |
| Sewer | 1/11/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 1/11/2022 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 1/14/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Corrections Issued | CLAYTON GRAHAM |
| Deputy Wood Construction | 3/3/2022 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 3/9/2022 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 3/16/2022 | Corrections Issued | PATRICK QUALEY |
| Rough-Elec/Plmb/HVAC | 3/16/2022 | Not Ready for Inspection | PATRICK QUALEY |
| BUILDING-Rough-Frame | 3/21/2022 | Corrections Issued | PATRICK QUALEY |
| ELECTRICAL-Rough | 3/21/2022 | Approved | PATRICK QUALEY |
| Green Building Rough | 3/21/2022 | Approved | PATRICK QUALEY |
| HVAC-Rough | 3/21/2022 | Corrections Issued | PATRICK QUALEY |
| Interior/Exterior Lathing | 3/21/2022 | Conditional Approval | PATRICK QUALEY |
| PLUMBING-Rough | 3/21/2022 | Approved | PATRICK QUALEY |
| Verify Sprinkler Sign Off | 3/21/2022 | Approved | PATRICK QUALEY |
| Insulation | 3/24/2022 | Approved | PATRICK QUALEY |
| Shower Pan | 3/24/2022 | Approved | PATRICK QUALEY |
| Drywall Nailing | 3/30/2022 | Partial Approval | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 3/30/2022 | Approved | CLAYTON GRAHAM |
| Smoke Detectors | 3/30/2022 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 4/27/2022 | Approved | PATRICK QUALEY |
| Drywall Nailing | 4/27/2022 | Approved | PATRICK QUALEY |
| ELECTRICAL-Final | 4/27/2022 | Corrections Issued | PATRICK QUALEY |
| Final | 4/27/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Footing/Foundation/Slab | 4/27/2022 | Approved | PATRICK QUALEY |
| Green Building Final | 4/27/2022 | Corrections Issued | PATRICK QUALEY |
| HVAC-Final | 4/27/2022 | Corrections Issued | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 4/27/2022 | SGSOV Not Required | PATRICK QUALEY |
| Service/Power Release | 4/27/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Smoke Detectors | 4/27/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Final | 5/23/2022 | Corrections Issued | PATRICK QUALEY |
| Green Building Final | 5/23/2022 | Approved | PATRICK QUALEY |
| Service/Power Release | 5/23/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Smoke Detectors | 5/23/2022 | Approved | PATRICK QUALEY |
| Final | 6/2/2022 | Corrections Issued | PATRICK QUALEY |
| Service/Power Release | 6/2/2022 | Approved | PATRICK QUALEY |
| Final | 6/7/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Service/Power Release | 6/7/2022 | Approved | PATRICK QUALEY |
| Final | 6/8/2022 | Corrections Issued | PATRICK QUALEY |
| Final | 8/25/2022 | OK to Issue CofO | JESUS RODRIGUEZ |