848 S GLENMONT AVE 90024
Certificate Information: 848 S GLENMONT AVE 90024
- Application / Permit
- 21010-10000-00010
- Plan Check / Job No.
- B21LA00038
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- 12'-9"X8' NEW DETACHED TRELLIS CONSTRUCTION BY STEEL BEAMS AND COLUMNS. 1 OF 3
- Permit Issued
- Issued on 2/24/2022
- Issuing Office
- Current Status
- Permit Closed on 4/26/2022
Permit Application Status History
| Submitted | 1/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | CHUNG-WEN CHUANG |
| Corrections Issued | 2/22/2021 | CHUNG-WEN CHUANG |
| Quality Review Completed | 2/23/2021 | JASON HEALEY |
| Applicant returned to address corrections | 8/3/2021 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 8/31/2021 | CHUNG-WEN CHUANG |
| Plan Check Approved | 12/7/2021 | CHUNG-WEN CHUANG |
| Issued | 2/24/2022 | APPLICANT |
| Building Plans Picked Up | 2/28/2022 | APPLICANT |
| Permit Closed | 4/25/2022 | BRENDAN LOONEY |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/31/2021 | MATTHEW JENKINS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jones,, Ryan Keith; Lic. No.: GE2852 | 1253 W MASLINE ST COVINA, CA 91722 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
| Engineer | Robles,, Gustavo; Lic. No.: C66797 | 981 W ARROW HWY 191 SAN DIMAS, CA 91773 |
| Geologist | Robles,, Gustavo; Lic. No.: EG2422 | 981 W. ARROW HIGHWAY #191 SAN DIMAS, CA 91773 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/2/2022 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 3/4/2022 | Partial Approval | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 3/10/2022 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/10/2022 | Approved | KEVIN SARGSYAN |
| Final | 4/25/2022 | Permit Closed | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Not Ready | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 4/25/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 4/25/2022 | Not Ready for Inspection | BRENDAN LOONEY |