7012 W LA PRESA DR 90068

Certificate Information: 7012 W LA PRESA DR 90068

Application / Permit
20047-70000-00363
Plan Check / Job No.
B20SL00410
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW IRREGULAR SHAPED SPA/SWIMMING POOL PER ENGINEERS DESIGN
Permit Issued
Issued on 9/25/2020
Issuing Office
Current Status
Issued on 9/25/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/10/2020 APPLICANT
Assigned to Plan Check Engineer 3/23/2020 LUKE GONZALES
Corrections Issued 3/26/2020 LUKE GONZALES
Quality Review Completed 3/31/2020 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 3/31/2020 APPLICANT
Applicant returned to address corrections 5/29/2020 LUKE GONZALES
Applicant returned to address corrections 9/15/2020 LUKE GONZALES
Plan Check Approved 9/17/2020 LUKE GONZALES
Issued 9/25/2020 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 4/27/2020 TRACY WILLIAMS
ZI Cleared 4/27/2020 TRACY WILLIAMS
Eng Process Fee Ord 176,300 Cleared 6/3/2020 ERIK BEASLEY
Roof/Waste drainage to street Cleared 6/3/2020 ERIK BEASLEY
Sewer availability Cleared 6/3/2020 ERIK BEASLEY
Grading Pre-Inspection Cleared 9/17/2020 LUKE GONZALES

Contact Information

Contractor Socal Construction & Design Inc; Lic. No.: 1045160-B 3289 VETERAN AVE      LOS ANGELES, CA 90025
Engineer Bustillos, Portillo, Alejandro Ivan; Lic. No.: C87257 4749 W 169TH STREET      LAWNDALE, CA 90260
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Geologist Triebold,, Mark John; Lic. No.: EG1796 6906 QUITO COURT      CAMARILLO, CA 93012

Inspector Information

BRIAN SULLIVAN, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Posting Pre-Inspection 12/21/2020 Corrections Issued BRIAN SULLIVAN
Piling/Pier/Caisson 1/7/2021 Not Ready for Inspection BRIAN SULLIVAN
Deputy Other (see comments) 1/13/2021 Conditional Approval BRIAN SULLIVAN
Deputy Other (see comments) 1/15/2021 Conditional Approval BRIAN SULLIVAN
Piling/Pier/Caisson 1/26/2021 Approved BRIAN SULLIVAN
Deputy Other (see comments) 1/27/2021 Conditional Approval BRIAN SULLIVAN
Deputy Other (see comments) 2/24/2021 Conditional Approval BRIAN SULLIVAN
Special/Order Compliance 3/3/2021 Not Ready for Inspection BRIAN SULLIVAN
Piling/Pier/Caisson 3/9/2021 Partial Approval BRIAN SULLIVAN
Deputy Other (see comments) 3/11/2021 Conditional Approval BRIAN SULLIVAN
Gas Piping or Gas Test 5/5/2022 Approved BRIAN SULLIVAN
Rough-Electrical 5/5/2022 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 5/17/2022 Not Ready for Inspection RUBEN SALAS
Excavation/Setback/Form/Re-Bar 5/19/2022 Approved AMY COLIN
Grounding or Bonding 5/19/2022 Approved AMY COLIN
Rough-Plumbing 5/19/2022 Approved AMY COLIN
Deputy Shotcrete 5/23/2022 Conditional Approval BRIAN SULLIVAN
Enclosure/Fence 9/16/2025 Corrections Issued BRIAN SULLIVAN