1499 W SEPULVEDA ST 90732
Certificate Information: 1499 W SEPULVEDA ST 90732
- Application / Permit
- 20047-40000-00261
- Plan Check / Job No.
- B20SP00199
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New Swimming Pool (15' x 27') with attached spa (7' x 7') per standard plan #268.
- Permit Issued
- Issued on 7/31/2020
- Issuing Office
- Current Status
- CofO Issued on 6/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2020 | CHRISTOPHER KOMANCHECK |
| Corrections Issued | 2/24/2020 | CHRISTOPHER KOMANCHECK |
| Applicant returned to address corrections | 5/21/2020 | FERNANDO FLORES |
| Building Plans Picked Up | 7/17/2020 | APPLICANT |
| Plan Check Approved | 7/31/2020 | KEVIN MORALES |
| Issued | 7/31/2020 | APPLICANT |
| CofO in Progress | 6/12/2025 | MICHAEL PELHAM |
| Permit Finaled | 6/12/2025 | RICHARD STEINBACH |
| CofO Issued | 6/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/24/2020 | CHRISTOPHER KOMANCHECK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/28/2020 | Conditional Approval | JOHN KLARIN |
| Deputy Shotcrete | 10/9/2020 | Approved | JOHN KLARIN |
| Rough-Electrical | 10/28/2020 | Approved | JOHN KLARIN |
| Grounding or Bonding | 12/10/2020 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 2/19/2021 | Approved | EUGENE CASSIDY |
| Final | 2/19/2021 | Corrections Issued | EUGENE CASSIDY |
| Pre-Gunite | 2/19/2021 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/19/2021 | SGSOV Approved | EUGENE CASSIDY |
| Pool Equipment Noise Test | 2/22/2021 | Approved | JAMES VORHIS |
| Final | 3/1/2021 | Corrections Issued | EUGENE CASSIDY |
| Final | 3/18/2021 | Corrections Issued | JOHN KLARIN |
| Final | 6/12/2025 | OK to Issue CofO | MICHAEL PELHAM |