1338 S COMSTOCK AVE 90024

Certificate Information: 1338 S COMSTOCK AVE 90024

Application / Permit
20047-30000-02340
Plan Check / Job No.
B20WL05631
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) pool at rear of lot.
Permit Issued
Issued on 3/15/2021
Issuing Office
Current Status
Issued on 3/15/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/28/2020 APPLICANT
Assigned to Plan Check Engineer 1/6/2021 VLADIMIR ARUTYUNYAN
Corrections Issued 1/20/2021 VLADIMIR ARUTYUNYAN
Quality Review Completed 1/28/2021 TARIK SAOUD
Building Plans Picked Up 1/29/2021 APPLICANT
Plan Check Approved 3/11/2021 VLADIMIR ARUTYUNYAN
Issued 3/15/2021 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Snow Construction; Lic. No.: 1016716-B 3268 HILLOCK DRIVE      LOS ANGELES, CA 90068
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/16/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Pre-Gunite 4/16/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Pre-Gunite 6/10/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Rough-Plumbing 6/10/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Grounding or Bonding 6/17/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Pre-Gunite 6/17/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Rough-Plumbing 6/17/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 6/21/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 6/21/2021 SGSOV Not Ready GERMAN RODRIGUEZ MENDOZA
Grounding or Bonding 6/23/2021 Partial Approval CHRISTOPHER WILSON
Pool Piping 6/23/2021 Approved CHRISTOPHER WILSON
Pre-Gunite 6/23/2021 Approved CHRISTOPHER WILSON
Rough-Electrical 6/23/2021 Partial Approval CHRISTOPHER WILSON
Enclosure/Fence 6/2/2022 Corrections Issued BRENDAN LOONEY
Enclosure/Fence 8/3/2022 Not Ready for Inspection CHRISTOPHER WILSON
Final 8/3/2022 Corrections Issued CHRISTOPHER WILSON
Enclosure/Fence 8/18/2022 Corrections Issued ANDREW NAVE
Deck 8/31/2022 Corrections Issued STEPHANIE SWANSON
Enclosure/Fence 8/31/2022 Corrections Issued STEPHANIE SWANSON
Pool/Spa Cover 8/31/2022 Not Ready for Inspection STEPHANIE SWANSON
Enclosure/Fence 9/1/2022 Corrections Issued STEPHANIE SWANSON
Deck 9/29/2022 Not Ready for Inspection STEPHANIE SWANSON
Enclosure/Fence 9/29/2022 Not Ready for Inspection STEPHANIE SWANSON
Deck 10/4/2022 Corrections Issued STEPHANIE SWANSON
Enclosure/Fence 10/4/2022 Corrections Issued STEPHANIE SWANSON
Deck 10/13/2022 Corrections Issued STEPHANIE SWANSON
Pool Equipment Noise Test 12/23/2022 No Access for Inspection JUSTIN CURTIS
Excavation/Setback/Form/Re-Bar 12/27/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Final 12/27/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 12/27/2022 SGSOV Not Ready GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 12/27/2022 Partial Approval ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 1/4/2023 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 1/4/2023 SGSOV Not Ready STEPHANIE SWANSON
Pool Equipment Noise Test 1/6/2023 Approved ROBERT CHAVEZ
Final 4/13/2023 No Access for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Not Ready CHRISTOPHER WILSON