10425 W SUNSET BLVD 90077

Certificate Information: 10425 W SUNSET BLVD 90077

Application / Permit
20047-30000-02231
Plan Check / Job No.
B20WL05405
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) SWIMMING POOL & SPA
Permit Issued
Issued on 6/28/2021
Issuing Office
Current Status
CofO Issued on 12/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 DAVID CASTILLO
Corrections Issued 2/1/2021 DAVID CASTILLO
Quality Review Completed 2/8/2021 TARIK SAOUD
Plan Check Approved 6/15/2021 DAVID CASTILLO
Issued 6/28/2021 APPLICANT
CofO in Progress 12/21/2024 CHRISTOPHER WILSON
Permit Finaled 12/24/2024 RICHARD STEINBACH
CofO Issued 12/24/2024 RICHARD STEINBACH
Permit Finaled 12/24/2024 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 2/19/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 2/24/2021 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 6/15/2021 DAVID CASTILLO

Contact Information

Contractor Owner-Builder       ,
Engineer Liston,, Leonard Irvin; Lic. No.: C31902 889 PIERCE CT STE 101      THOUSAND OAKS, CA 91360
Engineer Pond,, Britten Reis; Lic. No.: C71221 1024 CROWN HILL DR      SIMI VALLEY, CA 93063

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/26/2022 Partial Inspection ANDREW NAVE
FLOOD-Elevation Certificate 10/26/2022 Partial Approval ANDREW NAVE
Grounding or Bonding 10/26/2022 Corrections Issued ANDREW NAVE
Pool Piping 10/26/2022 Approved ANDREW NAVE
Grounding or Bonding 10/28/2022 Partial Approval CHRISTOPHER WILSON
Pre-Gunite 10/28/2022 Conditional Approval CHRISTOPHER WILSON
SWPPP-Const. Storm Water 10/28/2022 Completed CHRISTOPHER WILSON
Deputy Shotcrete 11/15/2022 Conditional Approval MICHAEL PELHAM
Pool Piping 2/2/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Rough-Electrical 2/2/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Rough-Plumbing 2/2/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Grounding or Bonding 3/20/2023 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 4/6/2023 Partial Approval CHRISTOPHER WILSON
Grounding or Bonding 4/6/2023 Partial Approval CHRISTOPHER WILSON
Gas Piping or Gas Test 5/22/2023 Corrections Issued CHRISTOPHER WILSON
Rough-Plumbing 5/22/2023 Not Ready for Inspection CHRISTOPHER WILSON
Enclosure/Fence 6/8/2023 Corrections Issued CHRISTOPHER WILSON
Enclosure/Fence 6/9/2023 Approved CHRISTOPHER WILSON
Final 6/20/2024 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 6/21/2024 SGSOV Not Ready CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/17/2024 Approved CHRISTOPHER WILSON
Final 10/17/2024 Corrections Issued CHRISTOPHER WILSON
Pre-Gunite 10/17/2024 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 10/17/2024 SGSOV Approved CHRISTOPHER WILSON
Pool Equipment Noise Test 10/22/2024 Not Ready for Inspection ANDEY CHAPARRO
Pool Equipment Noise Test 10/24/2024 Approved JUAN ESCOTO DELGADO
Final 11/4/2024 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 11/4/2024 Partial Inspection BOBBY KEY
Final 12/19/2024 OK to Issue CofO CHRISTOPHER WILSON