540 N BRISTOL AVE 90049

Certificate Information: 540 N BRISTOL AVE 90049

Application / Permit
20047-30000-02224
Plan Check / Job No.
B20WL05371
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) SWIMMING POOL (57'-5" X 11'-0" X 7"-3" DEEP) AND SPA (5'-7" X 7'-0" X 3'-9" DEEP ) PER STD PLAN 270
Permit Issued
Issued on 5/20/2021
Issuing Office
Current Status
CofO Issued on 8/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 KAVIAN REFAHI
Corrections Issued 12/26/2020 KAVIAN REFAHI
Applicant returned to address corrections 1/27/2021 JASON JANGADA
Applicant returned to address corrections 3/4/2021 ALFREDO JARA
Building Plans Picked Up 3/4/2021 APPLICANT
Plan Check Approved 5/3/2021 KHUONG TRUONG
Issued 5/20/2021 APPLICANT
CofO in Progress 7/27/2022 ANDREW NAVE
Permit Finaled 8/29/2022 DANIEL ORRANTE
CofO Issued 8/29/2022 DANIEL ORRANTE
Permit Finaled 8/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/26/2020 KAVIAN REFAHI
Construction near power lines Cleared 4/28/2021 WALTER RAMIREZ

Contact Information

Architect Radziner,, Ronald Mark; Lic. No.: C22228 MARMOL RADZINER & ASSOCIATES   12210 NEBRASKA AVE    LOS ANGELES, CA 90025
Contractor Tatum Construction Inc; Lic. No.: 733806-B 1909 CENTINELA AVENUE      SANTA MONICA, CA 90404
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 7/20/2021 Approved JUAN VALENZUELA
Gas Piping or Gas Test 9/24/2021 Partial Approval JUAN VALENZUELA
Grounding or Bonding 10/13/2021 Approved JUAN VALENZUELA
Solar System 10/13/2021 Not Ready for Inspection JUAN VALENZUELA
Enclosure/Fence 5/26/2022 Not Ready for Inspection BRENDAN LOONEY
Enclosure/Fence 6/1/2022 Corrections Issued JUAN VALENZUELA
Equipment Noise Level 6/29/2022 Approved AGUSTIN ALVAREZMORALES
Excavation/Setback/Form/Re-Bar 7/13/2022 Approved JUAN VALENZUELA
Final 7/13/2022 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 7/13/2022 SGSOV Not Ready JUAN VALENZUELA
Final 7/19/2022 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Approved KEVIN SARGSYAN
Final 7/27/2022 OK to Issue CofO ANDREW NAVE