8623 N STANSBURY AVE 91402
Certificate Information: 8623 N STANSBURY AVE 91402
- Application / Permit
- 20047-30000-02189
- Plan Check / Job No.
- B20WL05299
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL AND SPA PER STANDARD PLAN #268 AT REAR OF THE LOT .
- Permit Issued
- Issued on 4/15/2021
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 4/15/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2020 | JAHANSHAH POURHASSAN |
| Corrections Issued | 12/16/2020 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 4/15/2021 | MARJAN SHENASI |
| Issued | 4/15/2021 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/5/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Splash Pool Plastering Inc; Lic. No.: 979053-C53 | 15618 COBALT STREET SYLMAR, CA 91342 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/27/2021 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 1/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Gas Piping or Gas Test | 1/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Grounding or Bonding | 1/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Pool Piping | 1/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Pre-Gunite | 1/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Rough-Electrical | 1/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Rough-Plumbing | 1/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Gas Piping or Gas Test | 1/10/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Grounding or Bonding | 1/10/2022 | Approved | GREGG CUMMINGS |
| Pool Piping | 1/10/2022 | Approved | GREGG CUMMINGS |
| Pre-Gunite | 1/10/2022 | Approved | GREGG CUMMINGS |
| Gas Piping or Gas Test | 3/7/2022 | Corrections Issued | GREGG CUMMINGS |
| Gas Piping or Gas Test | 3/8/2022 | Partial Approval | GREGG CUMMINGS |
| Gas Piping or Gas Test | 6/27/2022 | No Access for Inspection | GREGG CUMMINGS |
| Gas Piping or Gas Test | 7/1/2022 | Approved | GREGG CUMMINGS |
| Deck | 7/20/2022 | Approved | GREGG CUMMINGS |
| Enclosure/Fence | 8/24/2022 | Approved | GREGG CUMMINGS |
| Pool Equipment Noise Test | 10/4/2022 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 11/7/2022 | Approved | GREGG CUMMINGS |
| Final | 11/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 11/7/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Final | 11/21/2022 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 11/21/2022 | SGSOV Approved | GREGG CUMMINGS |
| Final | 12/5/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Special/Order Compliance | 12/5/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 12/27/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Special/Order Compliance | 12/27/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Equipment Noise Level | 4/7/2023 | No Access for Inspection | FELIPE PENICHE |