2332 S PROSSER AVE 90064

Certificate Information: 2332 S PROSSER AVE 90064

Application / Permit
20047-30000-02050
Plan Check / Job No.
B20WL05001
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 14' X 20' POOL W/ 6' X 6' SPA WITHIN POOL SHELL PER LA CITY STANDARD PLAN #270
Permit Issued
Issued on 3/4/2021
Issuing Office
Current Status
CofO Issued on 10/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 RICHARD GARCIA
Corrections Issued 11/28/2020 RICHARD GARCIA
Applicant returned to address corrections 1/21/2021 JENNIFER LEE
Plan Check Approved 3/4/2021 JENNIFER LEE
Issued 3/4/2021 APPLICANT
Building Plans Picked Up 3/5/2021 APPLICANT
CofO in Progress 9/23/2021 GERMAN RODRIGUEZ MENDOZA
CofO Issued 10/20/2021 DANIEL ORRANTE
Permit Finaled 10/20/2021 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/21/2021 RICHARD GARCIA

Contact Information

Contractor Marten Darin Construction Company; Lic. No.: 525472-C53 P O BOX 659      PACIFIC PALISADES, CA 90272
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 3/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
Pool Piping 3/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
Pre-Gunite 3/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
Rough-Electrical 3/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
Rough-Plumbing 3/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
Deck 5/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
Enclosure/Fence 7/16/2021 Approved GERMAN RODRIGUEZ MENDOZA
Equipment Noise Level 7/27/2021 Approved ROBERT CHAVEZ
Excavation/Setback/Form/Re-Bar 8/10/2021 Approved GERMAN RODRIGUEZ MENDOZA
Final 8/10/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 8/10/2021 SGSOV Not Ready GERMAN RODRIGUEZ MENDOZA
Final 8/31/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 8/31/2021 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Final 9/20/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA