438 N NORTH FARING ROAD 90077

Certificate Information: 438 N NORTH FARING ROAD 90077

Application / Permit
20047-30000-01941
Plan Check / Job No.
B20WL04742
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(n) proposed swimming pool
Permit Issued
Issued on 5/3/2021
Issuing Office
Current Status
CofO Issued on 8/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/4/2020 TARIK SAOUD
Corrections Issued 11/7/2020 TARIK SAOUD
Quality Review Completed 11/25/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/1/2020 APPLICANT
Applicant returned to address corrections 1/25/2021 TARIK SAOUD
Applicant returned to address corrections 3/4/2021 TARIK SAOUD
Plan Check Approved 4/16/2021 TARIK SAOUD
Issued 5/3/2021 APPLICANT
CofO in Progress 8/12/2022 CHRISTOPHER WILSON
CofO in Progress 8/12/2022 CHRISTOPHER WILSON
Permit Finaled 8/18/2022 DANIEL ORRANTE
CofO Issued 8/18/2022 DANIEL ORRANTE
Permit Finaled 8/18/2022 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 12/17/2020 NIKTA MOUSAVI
Eng Process Fee Ord 176,300 Cleared 1/7/2021 NIKTA MOUSAVI
Grading Pre-Inspection Cleared 3/4/2021 TARIK SAOUD
Miscellaneous Cleared 3/4/2021 TARIK SAOUD

Contact Information

Architect Bittoni,, Mark Christopher; Lic. No.: C34136 434 N GREENCRAIG ROAD      LOS ANGELES, CA 90049
Contractor Owner-Builder       ,
Engineer Obando,, Gaspar Eduardo; Lic. No.: C71382 1453 14TH ST STE A      SANTA MONICA, CA 90404
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342
Geologist Feffer,, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 8/16/2021 Not Ready for Inspection CHRISTOPHER WILSON
Piling/Pier/Caisson 8/16/2021 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 8/16/2021 Partial Approval CHRISTOPHER WILSON
Deputy Other (see comments) 8/26/2021 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/26/2021 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 8/26/2021 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 9/2/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/10/2021 Partial Approval MATT KELLERMAN
Piling/Pier/Caisson 9/10/2021 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 11/9/2021 Not Ready for Inspection CHRISTOPHER WILSON
Grounding or Bonding 11/9/2021 Not Ready for Inspection CHRISTOPHER WILSON
Pool Piping 11/9/2021 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Gunite 11/9/2021 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 11/10/2021 Approved CHRISTOPHER WILSON
Grounding or Bonding 11/10/2021 Partial Approval CHRISTOPHER WILSON
Pool Piping 11/10/2021 Approved CHRISTOPHER WILSON
Pre-Gunite 11/10/2021 Approved CHRISTOPHER WILSON
Rough-Electrical 11/10/2021 Partial Approval CHRISTOPHER WILSON
Enclosure/Fence 4/15/2022 Corrections Issued CHRISTOPHER WILSON
Enclosure/Fence 4/19/2022 Approved CHRISTOPHER WILSON
Pool Equipment Noise Test 6/13/2022 Approved JUSTIN CURTIS
Final 8/1/2022 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Approved CHRISTOPHER WILSON
Final 8/5/2022 OK to Issue CofO CHRISTOPHER WILSON