619 S MORENO AVE 90049

Certificate Information: 619 S MORENO AVE 90049

Application / Permit
20047-30000-01891
Plan Check / Job No.
B20WL04663
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New pool per engineer design
Permit Issued
Issued on 5/24/2021
Issuing Office
Current Status
CofO Issued on 3/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2020 APPLICANT
Assigned to Plan Check Engineer 11/4/2020 MARJAN SHENASI
Corrections Issued 11/5/2020 MARJAN SHENASI
Building Plans Picked Up 11/6/2020 APPLICANT
Applicant returned to address corrections 5/3/2021 KHUONG TRUONG
Plan Check Approved 5/13/2021 RICHARD GARCIA
Issued 5/24/2021 APPLICANT
CofO in Progress 3/21/2022 KENNETH NAGLE
Permit Finaled 3/22/2022 DANIEL ORRANTE
CofO Issued 3/22/2022 DANIEL ORRANTE
Permit Finaled 3/22/2022 DANIEL ORRANTE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Rumo Group Inc The; Lic. No.: 1043968-B 2101 VETERAN AVE      LOS ANGELES, CA 90025
Engineer Azizisefat,, Solayman; Lic. No.: C57840 19510 VENTURA BLVD STE 110      TARZANA, CA 91356

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/10/2021 Approved OGANES TARAKHCHYAN
Grading Pre-Inspection 8/10/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Pre-Inspection 8/10/2021 Partial Approval OGANES TARAKHCHYAN
Pool Piping 10/26/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 10/27/2021 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 11/3/2021 Partial Approval OGANES TARAKHCHYAN
Grounding or Bonding 1/31/2022 Approved OGANES TARAKHCHYAN
Pool/Spa Cover 1/31/2022 Approved OGANES TARAKHCHYAN
Rough-Electrical 1/31/2022 Approved OGANES TARAKHCHYAN
Pool Equipment Noise Test 3/1/2022 Approved JAMES VORHIS
ELECTRICAL-Final 3/15/2022 Approved OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 3/15/2022 Approved OGANES TARAKHCHYAN
Final 3/15/2022 Partial Approval OGANES TARAKHCHYAN
Pre-Gunite 3/15/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/15/2022 SGSOV Approved OGANES TARAKHCHYAN