1244 N MORAGA DR 90049
Certificate Information: 1244 N MORAGA DR 90049
- Application / Permit
- 20047-30000-01830
- Plan Check / Job No.
- B20WL04547
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 61'-5" X 22'-4" SWIMMING POOL AND 12'-0" X 22'-4" SPA WITHIN PER STANDARD PLAN #268 AND ENGINEER DETAIL.
- Permit Issued
- Issued on 12/21/2020
- Issuing Office
- Current Status
- CofO Issued on 11/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2020 | MANUEL GARCIA |
| Corrections Issued | 10/28/2020 | MANUEL GARCIA |
| Building Plans Picked Up | 10/30/2020 | APPLICANT |
| Plan Check Approved | 12/3/2020 | JEROME MAGAT PALMA |
| Issued | 12/21/2020 | APPLICANT |
| CofO in Progress | 11/9/2022 | MICHAEL PELHAM |
| Permit Finaled | 11/15/2022 | DANIEL ORRANTE |
| CofO Issued | 11/15/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/15/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 11/12/2020 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 11/12/2020 | STEVEN WECHSLER |
| ZA Case | Cleared | 11/12/2020 | STEVEN WECHSLER |
| ZI | Cleared | 11/12/2020 | STEVEN WECHSLER |
Contact Information
| Contractor | Aqua Blue Pools; Lic. No.: 759633-C53 | 501-I S REINO ROAD #172 NEWBURY PARK, CA 91320 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/11/2021 | Approved | CARLOS MATAMOROS |
| FLOOD-Elevation Certificate | 2/11/2021 | Approved | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 2/11/2021 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 2/11/2021 | Approved | CARLOS MATAMOROS |
| Pool Piping | 2/11/2021 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 2/11/2021 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 2/11/2021 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 2/11/2021 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 10/22/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Enclosure/Fence | 11/12/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Enclosure/Fence | 11/16/2021 | Approved | CARLOS MATAMOROS |
| Final | 3/11/2022 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 3/11/2022 | SGSOV Approved | CARLOS MATAMOROS |
| Final | 4/6/2022 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 4/19/2022 | Approved | CARLOS MATAMOROS |
| Final | 4/19/2022 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 4/19/2022 | Approved | CARLOS MATAMOROS |
| Final | 10/19/2022 | Corrections Issued | CARLOS MATAMOROS |
| Final | 11/9/2022 | OK to Issue CofO | MICHAEL PELHAM |