114 S BEACHWOOD DR 90004

Certificate Information: 114 S BEACHWOOD DR 90004

Application / Permit
20047-30000-01801
Plan Check / Job No.
B20WL04509
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL AND SPA PER STANDARD PLAN #268.
Permit Issued
Issued on 4/7/2021
Issuing Office
Current Status
CofO Issued on 4/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2020 APPLICANT
Assigned to Plan Check Engineer 10/27/2020 MANUEL GARCIA
Corrections Issued 10/27/2020 MANUEL GARCIA
Applicant returned to address corrections 1/24/2021 RICHARD GARCIA
Plan Check Approved 1/25/2021 RICHARD GARCIA
No Progress 1/25/2021 RICHARD GARCIA
Plan Check Approved 2/4/2021 RICHARD GARCIA
Building Plans Picked Up 2/4/2021 APPLICANT
Issued 4/7/2021 APPLICANT
CofO in Progress 3/3/2023 RICHARD DOCKUS
CofO Issued 4/15/2023 DEROLD HAUFF
Permit Finaled 4/15/2023 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 11/9/2020 SUKI GERSHENHORN
Miscellaneous Cleared 11/9/2020 SUKI GERSHENHORN
Miscellaneous Cleared 11/9/2020 SUKI GERSHENHORN
Miscellaneous Cleared 11/9/2020 SUKI GERSHENHORN
ZI Cleared 11/9/2020 SUKI GERSHENHORN
Construction near power lines Cleared 1/9/2021 RIDWAN HARDY

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-B 15021 VENTURA BLVD STE 520      SHERMAN OAKS, CA 91403
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/23/2021 Approved CHRIS CHRISTENSEN
Gas Piping or Gas Test 6/23/2021 Approved CHRIS CHRISTENSEN
Pool Piping 6/23/2021 Approved CHRIS CHRISTENSEN
Posting Pre-Inspection 6/23/2021 Approved CHRIS CHRISTENSEN
Pre-Gunite 6/23/2021 Approved CHRIS CHRISTENSEN
Pre-Inspection 6/23/2021 Approved CHRIS CHRISTENSEN
Rough-Electrical 6/23/2021 Approved CHRIS CHRISTENSEN
Rough-Plumbing 6/23/2021 Approved CHRIS CHRISTENSEN
Deputy Shotcrete 7/6/2021 Conditional Approval CHRIS CHRISTENSEN
Grounding or Bonding 7/29/2021 Approved ARTHUR SARGSYAN
Enclosure/Fence 10/1/2021 Approved ARTHUR SARGSYAN
Final 12/8/2021 Corrections Issued ARTHUR SARGSYAN
Pool Equipment Noise Test 12/8/2021 Not Ready for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/8/2021 SGSOV Approved ARTHUR SARGSYAN
Final 12/30/2021 Corrections Issued CHRIS CHRISTENSEN
Pool Equipment Noise Test 1/3/2022 Approved JUSTIN CURTIS
Final 1/4/2022 Conditional Approval CHRIS CHRISTENSEN
Final 11/14/2022 Corrections Issued JULIAN AMAYA
Final 2/10/2023 No Access for Inspection MICHAEL LEWIS
Final 3/2/2023 OK to Issue CofO RICHARD DOCKUS