519 N LAUREL AVE 90048
Certificate Information: 519 N LAUREL AVE 90048
- Application / Permit
- 20047-30000-01669
- Plan Check / Job No.
- B20WL04227
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL AND SPA 5' DEEP MAX. AT REAR OF LOT
- Permit Issued
- Issued on 11/10/2020
- Issuing Office
- Current Status
- CofO Issued on 10/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2020 | JASON JANGADA |
| Corrections Issued | 10/6/2020 | JASON JANGADA |
| Applicant returned to address corrections | 10/21/2020 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 11/4/2020 | JASON JANGADA |
| Issued | 11/10/2020 | APPLICANT |
| Building Plans Picked Up | 11/10/2020 | APPLICANT |
| CofO in Progress | 10/6/2021 | CHRIS CHRISTENSEN |
| CofO in Progress | 10/7/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 10/8/2021 | DEROLD HAUFF |
| CofO Issued | 10/8/2021 | DEROLD HAUFF |
| Permit Finaled | 10/8/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/7/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Sunset Built Inc; Lic. No.: 1005054-B | 5455 WILSHIRE BLVD #1811 LOS ANGELES, CA 90036 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/14/2020 | Approved | STUART CHAPMAN |
| Pre-Gunite | 11/14/2020 | Approved | STUART CHAPMAN |
| Rough-Electrical | 11/14/2020 | Approved | STUART CHAPMAN |
| Rough-Plumbing | 11/14/2020 | Approved | STUART CHAPMAN |
| Grounding or Bonding | 6/17/2021 | Approved | CHRIS CHRISTENSEN |
| Enclosure/Fence | 8/20/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 9/2/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 9/2/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Pool Equipment Noise Test | 9/8/2021 | Approved | ROBERT CHAVEZ |
| Final | 10/6/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |