14732 W TUSTIN ST 91403

Certificate Information: 14732 W TUSTIN ST 91403

Application / Permit
20047-30000-01651
Plan Check / Job No.
B20WL04196
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
alteration of existing pool and spa
Permit Issued
Issued on 3/12/2021
Issuing Office
Current Status
CofO Issued on 4/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2020 APPLICANT
Assigned to Plan Check Engineer 10/21/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 11/24/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 12/4/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/9/2020 APPLICANT
Plan Check Approved 1/31/2021 VLADIMIR ARUTYUNYAN
Issued 3/12/2021 APPLICANT
CofO in Progress 12/9/2022 MATTHEW NELSON
Permit Finaled 4/1/2023 DANIEL ORRANTE
CofO Issued 4/1/2023 DANIEL ORRANTE
Permit Finaled 4/1/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/31/2021 VLADIMIR ARUTYUNYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/27/2021 Corrections Issued CHARLES POWELL
Pool Piping 4/27/2021 Not Ready for Inspection CHARLES POWELL
Rough-Electrical 4/27/2021 Not Ready for Inspection CHARLES POWELL
Rough-Plumbing 4/27/2021 Not Ready for Inspection CHARLES POWELL
Excavation/Setback/Form/Re-Bar 5/19/2021 Not Ready for Inspection CHARLES POWELL
Pre-Gunite 5/19/2021 Not Ready for Inspection CHARLES POWELL
Rough-Electrical 5/19/2021 Not Ready for Inspection CHARLES POWELL
Rough-Plumbing 5/19/2021 Not Ready for Inspection CHARLES POWELL
Pool Piping 6/17/2021 Approved CHARLES POWELL
Pre-Gunite 6/17/2021 Partial Approval CHARLES POWELL
Rough-Electrical 6/17/2021 Approved CHARLES POWELL
Rough-Plumbing 6/17/2021 Approved CHARLES POWELL
Deputy Shotcrete 7/9/2021 Conditional Approval DANIEL ORRANTE
Gas Piping or Gas Test 8/17/2021 Approved ALIZAH MAYAGOITIA
Grounding or Bonding 8/26/2021 Not Ready for Inspection CHARLES POWELL
Grounding or Bonding 9/2/2021 Not Ready for Inspection CHARLES POWELL
Grounding or Bonding 9/7/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Deck 9/8/2021 Approved CHRISTOPHER DELLEFIELD
Grounding or Bonding 9/8/2021 Approved CHRISTOPHER DELLEFIELD
Pre-Inspection 10/27/2021 Corrections Issued JACK KARGODORIAN
Enclosure/Fence 11/1/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Special/Order Compliance 11/5/2021 Corrections Issued JACK KARGODORIAN
Enclosure/Fence 11/9/2021 Approved JACK KARGODORIAN
Pre-Inspection 11/9/2021 Partial Inspection JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 11/22/2021 Approved CHRISTOPHE COCHRAN
Final 11/22/2021 Corrections Issued CHRISTOPHE COCHRAN
Pool Equipment Noise Test 11/22/2021 Approved ALFREDO FLORES
Pre-Gunite 11/22/2021 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 11/22/2021 SGSOV Not Ready CHRISTOPHE COCHRAN
Final 11/4/2022 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 11/4/2022 SGSOV Not Ready THOMAS FINNILA
Final 11/23/2022 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 11/23/2022 SGSOV Not Ready THOMAS FINNILA
Final 12/2/2022 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Approved MISAEL ESPARZA
ELECTRICAL-Final 12/8/2022 Approved MATTHEW NELSON
Final 12/8/2022 OK to Issue CofO MATTHEW NELSON