555 S BURLINGAME AVE 90049
Certificate Information: 555 S BURLINGAME AVE 90049
- Application / Permit
- 20047-30000-01554
- Plan Check / Job No.
- B20WL04002
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Remodel and lengthen existing pool, remodel existing spa, replace pool equipment in same location per standard plan#268
- Permit Issued
- Issued on 11/9/2020
- Issuing Office
- Current Status
- CofO Issued on 6/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | JASON JANGADA |
| Corrections Issued | 9/18/2020 | JASON JANGADA |
| Applicant returned to address corrections | 10/20/2020 | KAVIAN REFAHI |
| Plan Check Approved | 11/5/2020 | JASON JANGADA |
| Issued | 11/9/2020 | APPLICANT |
| Building Plans Picked Up | 11/13/2020 | APPLICANT |
| CofO in Progress | 6/10/2025 | MICHAEL PELHAM |
| Permit Finaled | 6/10/2025 | RICHARD STEINBACH |
| CofO Issued | 6/10/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/10/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZA Case | Cleared | 10/27/2020 | SARAHI ORTEGA |
| ZA Case | Cleared | 10/27/2020 | SARAHI ORTEGA |
| ZA Case | Cleared | 10/27/2020 | SARAHI ORTEGA |
| ZA Case | Cleared | 10/27/2020 | SARAHI ORTEGA |
| ZA Case | Cleared | 10/27/2020 | SARAHI ORTEGA |
Contact Information
| Contractor | J D S S Construction Company Inc; Lic. No.: 425872-B | 1702 S ROBERTSON BLVD #285 LOS ANGELES, CA 90035 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 1/8/2021 | Approved | OGANES TARAKHCHYAN |
| Gas Piping or Gas Test | 1/15/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Piping or Gas Test | 1/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 4/11/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/11/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 6/10/2025 | OK to Issue CofO | MICHAEL PELHAM |