640 E MILWOOD AVE 90291
Certificate Information: 640 E MILWOOD AVE 90291
- Application / Permit
- 20047-30000-01469
- Plan Check / Job No.
- B20WL03888
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 14' X 6'-6" POOL PER LACITY STANDARD PLAN #268
- Permit Issued
- Issued on 6/5/2021
- Issuing Office
- Current Status
- CofO Issued on 6/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | MANUEL GARCIA |
| Corrections Issued | 10/1/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 10/7/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 1/2/2021 | RICHARD GARCIA |
| Plan Check Approved | 5/18/2021 | OMAR GARNICA |
| Building Plans Picked Up | 5/19/2021 | APPLICANT |
| Issued | 6/5/2021 | APPLICANT |
| CofO in Progress | 5/27/2022 | RICHARD STEINBACH |
| Permit Finaled | 6/1/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/1/2022 | DANIEL ORRANTE |
| CofO Issued | 6/1/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Coastal Zone | Cleared | 5/12/2021 | NOAH MCCOY |
| Miscellaneous | Cleared | 5/12/2021 | NOAH MCCOY |
| Miscellaneous | Cleared | 5/12/2021 | NOAH MCCOY |
| Miscellaneous | Cleared | 5/12/2021 | NOAH MCCOY |
| Miscellaneous | Cleared | 5/12/2021 | NOAH MCCOY |
| Specific Plan | Cleared | 5/12/2021 | NOAH MCCOY |
Contact Information
| Contractor | Avanti Pools Inc; Lic. No.: 772516-C53 | 8138 ORION AVE VAN NUYS, CA 91406 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/29/2021 | Corrections Issued | JOHNNY MIRANDA |
| Pre-Gunite | 7/2/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Gas Piping or Gas Test | 7/28/2021 | Approved | MORRIS JACKSON |
| Deck | 8/26/2021 | Approved | JOHNNY MIRANDA |
| Enclosure/Fence | 3/11/2022 | Conditional Approval | JOHNNY MIRANDA |
| Equipment Noise Level | 4/8/2022 | Not Ready for Inspection | JAMES VORHIS |
| Equipment Noise Level | 4/21/2022 | Approved | JAMES VORHIS |
| Excavation/Setback/Form/Re-Bar | 5/26/2022 | Approved | JESUS RODRIGUEZ |
| Final | 5/26/2022 | OK to Issue CofO | JESUS RODRIGUEZ |
| Pre-Gunite | 5/26/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/26/2022 | SGSOV Approved | JESUS RODRIGUEZ |