3225 S CLUB DR 90064
Certificate Information: 3225 S CLUB DR 90064
- Application / Permit
- 20047-30000-01461
- Plan Check / Job No.
- B20WL03879
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New swimming pool and spa per LA city standard plan #268
- Permit Issued
- Issued on 9/18/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | REZA HAGHIGHAT |
| Corrections Issued | 9/7/2020 | REZA HAGHIGHAT |
| Plan Check Approved | 9/17/2020 | JASON JANGADA |
| Issued | 9/18/2020 | APPLICANT |
| Building Plans Picked Up | 9/21/2020 | APPLICANT |
| CofO Issued | 7/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/5/2020 | REZA HAGHIGHAT |
| Specific Plan | Cleared | 9/8/2020 | DYLAN SITTIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 10/19/2020 | Approved | KEVIN SARGSYAN |
| Pre-Gunite | 10/19/2020 | Conditional Approval | KEVIN SARGSYAN |
| Rough-Electrical | 10/19/2020 | Approved | KEVIN SARGSYAN |
| Rough-Plumbing | 10/19/2020 | Approved | KEVIN SARGSYAN |
| Deputy Shotcrete | 10/27/2020 | Conditional Approval | KEVIN SARGSYAN |
| Enclosure/Fence | 2/16/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Enclosure/Fence | 2/17/2021 | Approved | RICHARD ROBLES |
| Rough-Electrical | 2/17/2021 | Approved | RICHARD ROBLES |
| Equipment Noise Level | 3/11/2021 | Approved | DA LIU |
| Excavation/Setback/Form/Re-Bar | 3/18/2021 | Approved | KEVIN SARGSYAN |
| Final | 3/18/2021 | Conditional Approval | KEVIN SARGSYAN |
| Pre-Gunite | 3/18/2021 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2021 | SGSOV Approved | KEVIN SARGSYAN |