543 S MUIRFIELD ROAD 90020
Certificate Information: 543 S MUIRFIELD ROAD 90020
- Application / Permit
- 20047-30000-01424
- Plan Check / Job No.
- B20WL03750
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool and spa per engineered plans
- Permit Issued
- Issued on 2/1/2021
- Issuing Office
- Current Status
- CofO Issued on 9/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 9/30/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 10/9/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 1/31/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 2/1/2021 | APPLICANT |
| Building Plans Picked Up | 2/1/2021 | APPLICANT |
| CofO in Progress | 9/7/2022 | ALIZAH MAYAGOITIA |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
| CofO Issued | 9/11/2022 | DEROLD HAUFF |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 12/15/2020 | SUKI GERSHENHORN |
Contact Information
| Contractor | Minardos Group; Lic. No.: 728956-B | 2800 28TH STREET SUITE 170 SANTA MONICA, CA 90405 |
| Engineer | Peterson,, David John; Lic. No.: C58167 | 140 LOMAS SANTA FE DR STE 202 SOLANA BEACH, CA 92075 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/3/2021 | Approved | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 2/3/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Grounding or Bonding | 2/3/2021 | Partial Approval | JOSEPH MCGARRY |
| Pool Piping | 2/3/2021 | Approved | JOSEPH MCGARRY |
| Pre-Gunite | 2/3/2021 | Approved | JOSEPH MCGARRY |
| Rough-Electrical | 2/3/2021 | Approved | JOSEPH MCGARRY |
| Rough-Plumbing | 2/3/2021 | Approved | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 2/4/2021 | Approved | JOSEPH MCGARRY |
| Rough-Electrical | 4/8/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Rough-Plumbing | 4/8/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Enclosure/Fence | 7/7/2022 | Approved | ADAM ESCOTO |
| Final | 8/1/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/1/2022 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 8/18/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 9/7/2022 | OK to Issue CofO | ALIZAH MAYAGOITIA |