7911 S MCCONNELL AVE 90045
Certificate Information: 7911 S MCCONNELL AVE 90045
- Application / Permit
- 20047-30000-01400
- Plan Check / Job No.
- B20WL03731
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14' X 23' POOL WITH 7' X 7' SPA PER ( LA CITY STANDARD PLAN # 268/ ENGINEERING DESIGN).
- Permit Issued
- Issued on 1/21/2021
- Issuing Office
- Current Status
- CofO Issued on 8/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | PARISA ZAHABI |
| Corrections Issued | 9/7/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 9/21/2020 | JASON JANGADA |
| Applicant returned to address corrections | 12/24/2020 | JASON JANGADA |
| Plan Check Approved | 1/13/2021 | JASON JANGADA |
| Issued | 1/21/2021 | APPLICANT |
| Building Plans Picked Up | 1/22/2021 | APPLICANT |
| CofO in Progress | 8/2/2021 | BRENDAN LOONEY |
| CofO Issued | 8/10/2021 | VINCENT COTTON |
| Permit Finaled | 8/10/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/16/2020 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 12/24/2020 | PARISA ZAHABI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/23/2021 | Approved | BRENDAN LOONEY |
| Pre-Gunite | 3/23/2021 | Approved | BRENDAN LOONEY |
| Rough-Electrical | 3/23/2021 | Approved | BRENDAN LOONEY |
| Rough-Plumbing | 3/23/2021 | Approved | BRENDAN LOONEY |
| Deck | 6/10/2021 | Approved | BRENDAN LOONEY |
| Enclosure/Fence | 6/10/2021 | Approved | BRENDAN LOONEY |
| Final | 7/27/2021 | Corrections Issued | BRENDAN LOONEY |
| Pool/Spa Cover | 7/27/2021 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 7/27/2021 | SGSOV Approved | BRENDAN LOONEY |
| Final | 7/30/2021 | OK to Issue CofO | BRENDAN LOONEY |