12203 W OCTAGON ST 90049
Certificate Information: 12203 W OCTAGON ST 90049
- Application / Permit
- 20047-30000-01399
- Plan Check / Job No.
- B20WL03730
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 38' X 17'-2" POOL WITH 6'-0" X 7'-4" SPA PER ( LA CITY STANDARD PLAN # 268 / ENGINEERING DESIGN ).
- Permit Issued
- Issued on 6/4/2021
- Issuing Office
- Current Status
- CofO Issued on 5/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | PARISA ZAHABI |
| Corrections Issued | 9/7/2020 | PARISA ZAHABI |
| Plan Check Approved | 6/4/2021 | PARISA ZAHABI |
| Issued | 6/4/2021 | APPLICANT |
| Building Plans Picked Up | 6/7/2021 | APPLICANT |
| CofO in Progress | 5/2/2022 | MICHAEL PELHAM |
| Permit Finaled | 5/5/2022 | DANIEL ORRANTE |
| CofO Issued | 5/5/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/5/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 10/8/2020 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2020 | OSCAR GUTIERREZ |
| Miscellaneous | Cleared | 5/12/2021 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 6/4/2021 | PARISA ZAHABI |
Contact Information
| Contractor | Sierra Creek Pools And Spas Corp; Lic. No.: 993352-C53 | 17516 DOVE WILLOW STREET SANTA CLARITA, CA 91387 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/15/2021 | Corrections Issued | CARLOS MATAMOROS |
| Rough-Electrical | 6/15/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Special/Order Compliance | 6/16/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Grounding or Bonding | 6/17/2021 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 6/17/2021 | Partial Approval | CARLOS MATAMOROS |
| Rough-Electrical | 6/17/2021 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 6/17/2021 | Approved | CARLOS MATAMOROS |
| Deputy Shotcrete | 6/24/2021 | Partial Approval | MATT KELLERMAN |
| Deck | 8/6/2021 | Approved | JUAN VALENZUELA |
| Enclosure/Fence | 10/4/2021 | Corrections Issued | RYAN SALAZAR |
| Pre-Inspection | 10/4/2021 | Partial Inspection | STEPHANIE SWANSON |
| Enclosure/Fence | 10/7/2021 | Approved | JUAN VALENZUELA |
| Equipment Noise Level | 3/24/2022 | Approved | JAMES VORHIS |
| Final | 3/25/2022 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 3/25/2022 | SGSOV Approved | JUAN VALENZUELA |
| Final | 4/21/2022 | No Access for Inspection | JOHN KIDWELL |
| Final | 4/26/2022 | Corrections Issued | MICHAEL PELHAM |
| Final | 5/2/2022 | OK to Issue CofO | MICHAEL PELHAM |