10112 W CHEVIOT DR 90064
Certificate Information: 10112 W CHEVIOT DR 90064
- Application / Permit
- 20047-30000-01327
- Plan Check / Job No.
- B20WL03571
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL & SPA
- Permit Issued
- Issued on 9/22/2020
- Issuing Office
- Current Status
- CofO Issued on 5/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2020 | KAVIAN REFAHI |
| Corrections Issued | 8/25/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 9/9/2020 | JASON JANGADA |
| Plan Check Approved | 9/21/2020 | JASON JANGADA |
| Issued | 9/22/2020 | APPLICANT |
| Building Plans Picked Up | 9/24/2020 | APPLICANT |
| CofO in Progress | 4/16/2021 | KEVIN SARGSYAN |
| Permit Finaled | 5/4/2021 | KENNETH NAGLE |
| CofO Issued | 5/4/2021 | KENNETH NAGLE |
| Permit Finaled | 5/4/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Shore Real Estate Development; Lic. No.: 914609-B | 270 N CANON DRIVE 3RD FLOOR BEVERLY HILLS, CA 90210 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/16/2020 | Approved | EVAN COOPER |
| Rough-Plumbing | 10/16/2020 | Partial Approval | EVAN COOPER |
| Deputy Shotcrete | 10/22/2020 | No Access for Inspection | KENNETH NAGLE |
| Deck | 12/18/2020 | Approved | KEVIN SARGSYAN |
| Grounding or Bonding | 12/18/2020 | Approved | KEVIN SARGSYAN |
| Enclosure/Fence | 3/3/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Equipment Noise Level | 3/17/2021 | Approved | DA LIU |
| Final | 4/13/2021 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Gunite | 4/13/2021 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 4/16/2021 | OK to Issue CofO | KEVIN SARGSYAN |