586-588 E GRAND BLVD 90291

Certificate Information: 586-588 E GRAND BLVD 90291

Application / Permit
20047-30000-01282
Plan Check / Job No.
B19WL07154
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) pool & spa
Permit Issued
Issued on 2/1/2021
Issuing Office
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Green Plans Picked Up 1/15/2020 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 1/23/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 1/31/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/28/2020 VLADIMIR ARUTYUNYAN
Plan Check Approved 1/28/2021 VLADIMIR ARUTYUNYAN
Plan Check Approved 1/28/2021 VLADIMIR ARUTYUNYAN
Plan Check Approved 1/31/2021 VLADIMIR ARUTYUNYAN
Plan Check Approved 1/31/2021 VLADIMIR ARUTYUNYAN
Issued 2/1/2021 APPLICANT
Building Plans Picked Up 2/1/2021 APPLICANT
CofO in Progress 10/2/2025 JESUS RODRIGUEZ
Permit Finaled 10/7/2025 RICHARD STEINBACH
CofO Issued 10/7/2025 RICHARD STEINBACH
Permit Finaled 10/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Coastal Zone Cleared 8/19/2020 DENZEL HENDERSON
Specific Plan Cleared 8/19/2020 DENZEL HENDERSON
ZA Case Cleared 8/19/2020 DENZEL HENDERSON
ZA Case Cleared 8/19/2020 DENZEL HENDERSON
ZA Case Cleared 8/19/2020 DENZEL HENDERSON
ZA Case Cleared 8/19/2020 DENZEL HENDERSON

Contact Information

Architect Lund,, Priti; Lic. No.: C33406 1820 ASHMORZ PLACE      LOS ANGELES, CA 90026
Contractor Owner-Builder       ,
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/13/2022 Partial Approval EVAN COOPER
Pool Piping 12/14/2023 Approved HERBERT GIRON
Pre-Gunite 12/14/2023 Approved HERBERT GIRON
Deputy Shotcrete 12/19/2023 Conditional Approval HERBERT GIRON
Enclosure/Fence 6/16/2025 Approved JESUS RODRIGUEZ
Grounding or Bonding 6/16/2025 Approved JESUS RODRIGUEZ
Pool Equipment Noise Test 7/11/2025 Approved EUSEBIO GUZMAN
ELECTRICAL-Final 7/15/2025 Approved JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 7/15/2025 Approved JESUS RODRIGUEZ
Final 7/15/2025 Conditional Approval JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/15/2025 SGSOV Approved JESUS RODRIGUEZ
ELECTRICAL-Final 9/23/2025 Approved JESUS RODRIGUEZ
Final 9/23/2025 OK to Issue CofO JESUS RODRIGUEZ