11620 W FRANCIS PL 90066
Certificate Information: 11620 W FRANCIS PL 90066
- Application / Permit
- 20047-30000-01195
- Plan Check / Job No.
- B20WL03281
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool with attached spa per std plan 268.
- Permit Issued
- Issued on 1/20/2021
- Issuing Office
- Current Status
- CofO Issued on 1/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2020 | JASON JANGADA |
| Corrections Issued | 8/6/2020 | JASON JANGADA |
| Applicant returned to address corrections | 8/13/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 8/20/2020 | ALFREDO JARA |
| Plan Check Approved | 1/5/2021 | MANUEL GARCIA |
| Issued | 1/20/2021 | APPLICANT |
| Building Plans Picked Up | 1/21/2021 | APPLICANT |
| CofO in Progress | 1/6/2022 | JOHNNY MIRANDA |
| Permit Finaled | 1/19/2022 | KENNETH NAGLE |
| CofO Issued | 1/19/2022 | KENNETH NAGLE |
| Permit Finaled | 1/19/2022 | KENNETH NAGLE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/24/2020 | JASON JANGADA |
| Construction near power lines | Cleared | 12/16/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/1/2021 | Approved | RICHARD ROBLES |
| Gas Piping or Gas Test | 2/1/2021 | Approved | RICHARD ROBLES |
| Pool Piping | 2/1/2021 | Approved | RICHARD ROBLES |
| Pre-Gunite | 2/1/2021 | Approved | RICHARD ROBLES |
| Rough-Electrical | 2/1/2021 | Partial Approval | RICHARD ROBLES |
| Rough-Plumbing | 2/1/2021 | Approved | RICHARD ROBLES |
| Deputy Shotcrete | 2/3/2021 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 2/3/2021 | Approved | RICHARD ROBLES |
| Pool Piping | 2/3/2021 | Approved | RICHARD ROBLES |
| Pre-Gunite | 2/3/2021 | Approved | RICHARD ROBLES |
| Rough-Electrical | 2/3/2021 | Approved | RICHARD ROBLES |
| Rough-Plumbing | 2/3/2021 | Approved | RICHARD ROBLES |
| Grounding or Bonding | 5/4/2021 | Partial Approval | EVAN COOPER |
| Grounding or Bonding | 5/27/2021 | Approved | OGANES TARAKHCHYAN |
| Enclosure/Fence | 8/31/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Enclosure/Fence | 9/7/2021 | Approved | OGANES TARAKHCHYAN |
| Equipment Noise Level | 12/1/2021 | Not Ready for Inspection | JAMES VORHIS |
| Final | 12/2/2021 | Corrections Issued | JOHNNY MIRANDA |
| Pool/Spa Cover | 12/2/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Equipment Noise Level | 12/7/2021 | Approved | JAMES VORHIS |
| Final | 12/8/2021 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 12/8/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Final | 12/14/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 12/14/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Final | 12/17/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 12/17/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Final | 12/27/2021 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 12/27/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Final | 1/6/2022 | OK to Issue CofO | JOHNNY MIRANDA |