4246 N RIVERTON AVE 91602
Certificate Information: 4246 N RIVERTON AVE 91602
- Application / Permit
- 20047-30000-01157
- Plan Check / Job No.
- B20WL03209
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool per standard plan # 268 at rear of the lot. ***1 of 2***
- Permit Issued
- Issued on 11/19/2020
- Issuing Office
- Current Status
- CofO Issued on 8/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2020 | JASON JANGADA |
| Corrections Issued | 8/3/2020 | JASON JANGADA |
| Applicant returned to address corrections | 11/13/2020 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 11/18/2020 | JAHANSHAH POURHASSAN |
| Issued | 11/19/2020 | APPLICANT |
| Building Plans Picked Up | 11/25/2020 | APPLICANT |
| CofO in Progress | 7/1/2021 | ARAM AVEDISIAN |
| CofO Issued | 8/7/2021 | MICHAEL SMITH |
| Permit Finaled | 8/7/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/8/2020 | TORI CHEN |
| Construction within easement | Cleared | 10/8/2020 | TORI CHEN |
Contact Information
| Architect | , ; Lic. No.: C5746 | SHERMAN OAKS, |
| Contractor | C & C Building And Landscaping Inc; Lic. No.: 923662-B | 5076 G STREET CHINO, CA 91710 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/15/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Pool Piping | 12/23/2020 | Partial Approval | THOMAS FINNILA |
| Pre-Gunite | 12/23/2020 | Conditional Approval | THOMAS FINNILA |
| Deputy Shotcrete | 1/11/2021 | Conditional Approval | THOMAS FINNILA |
| Gas Piping or Gas Test | 1/15/2021 | Approved | THOMAS FINNILA |
| Deck | 1/29/2021 | Approved | THOMAS FINNILA |
| Enclosure/Fence | 3/8/2021 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 3/25/2021 | Approved | ARAM AVEDISIAN |
| Equipment Noise Level | 3/31/2021 | No Access for Inspection | FELIPE PENICHE |
| Final | 4/1/2021 | No Access for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/1/2021 | SGSOV Not Ready | THOMAS FINNILA |
| Equipment Noise Level | 4/7/2021 | Approved | FELIPE PENICHE |
| Final | 4/12/2021 | Partial Approval | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/12/2021 | SGSOV Approved | THOMAS FINNILA |
| Final | 7/1/2021 | OK to Issue CofO | ARAM AVEDISIAN |