16103 W SANDY LANE 91436
Certificate Information: 16103 W SANDY LANE 91436
- Application / Permit
- 20047-30000-01039
- Plan Check / Job No.
- B20WL02905
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (E) 40' X 15' POOL TO BE MODIFIED INTO 32'-9.5" X 15'-3" RECTANGULAR POOL AND BAJA SHELF WITH (N) 7'-2" X 8'-6" SPA WITHING THE POOL. LA CITY STANDARD PLAN # 254 /ENGINEERED DESIGN).
- Permit Issued
- Issued on 12/17/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | PARISA ZAHABI |
| Corrections Issued | 7/16/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 9/22/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 10/28/2020 | MANUEL GARCIA |
| Plan Check Approved | 12/11/2020 | KAVIAN REFAHI |
| Issued | 12/17/2020 | APPLICANT |
| Building Plans Picked Up | 12/17/2020 | APPLICANT |
| CofO in Progress | 9/10/2021 | RONALD COWAN |
| Permit Finaled | 12/11/2021 | MICHAEL SMITH |
| CofO Issued | 12/11/2021 | MICHAEL SMITH |
| Permit Finaled | 12/11/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Specific Plan | Cleared | 7/20/2020 | SHEILA GERSHON |
| ZA Case | Cleared | 7/20/2020 | SHEILA GERSHON |
| ZA Case | Cleared | 7/20/2020 | SHEILA GERSHON |
| Grading Pre-Inspection | Cleared | 11/13/2020 | PARISA ZAHABI |
Contact Information
| Contractor | Vision Construction; Lic. No.: 541505-B | 6012 TOPEKA DRIVE TARZANA, CA 91356 |
| Engineer | Azizisefat,, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/6/2021 | Approved | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 1/7/2021 | Conditional Approval | RONALD COWAN |
| Pre-Gunite | 1/7/2021 | Conditional Approval | RONALD COWAN |
| Deck | 5/10/2021 | Partial Approval | MICHAEL PELHAM |
| Enclosure/Fence | 8/9/2021 | Partial Inspection | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 8/9/2021 | SGSOV Not Ready | RONALD COWAN |
| Enclosure/Fence | 8/13/2021 | Partial Approval | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 8/13/2021 | SGSOV Not Ready | RONALD COWAN |
| Final | 8/25/2021 | Corrections Issued | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 8/25/2021 | SGSOV Not Ready | PETER FOLLING |
| Pool Equipment Noise Test | 9/2/2021 | Approved | FELIPE PENICHE |
| Final | 9/10/2021 | OK to Issue CofO | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 9/10/2021 | SGSOV Approved | RONALD COWAN |