16103 W SANDY LANE 91436

Certificate Information: 16103 W SANDY LANE 91436

Application / Permit
20047-30000-01039
Plan Check / Job No.
B20WL02905
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(E) 40' X 15' POOL TO BE MODIFIED INTO 32'-9.5" X 15'-3" RECTANGULAR POOL AND BAJA SHELF WITH (N) 7'-2" X 8'-6" SPA WITHING THE POOL. LA CITY STANDARD PLAN # 254 /ENGINEERED DESIGN).
Permit Issued
Issued on 12/17/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 PARISA ZAHABI
Corrections Issued 7/16/2020 PARISA ZAHABI
Applicant returned to address corrections 9/22/2020 PARISA ZAHABI
Applicant returned to address corrections 10/28/2020 MANUEL GARCIA
Plan Check Approved 12/11/2020 KAVIAN REFAHI
Issued 12/17/2020 APPLICANT
Building Plans Picked Up 12/17/2020 APPLICANT
CofO in Progress 9/10/2021 RONALD COWAN
Permit Finaled 12/11/2021 MICHAEL SMITH
CofO Issued 12/11/2021 MICHAEL SMITH
Permit Finaled 12/11/2021 MICHAEL SMITH

Permit Application Clearance Information

Specific Plan Cleared 7/20/2020 SHEILA GERSHON
ZA Case Cleared 7/20/2020 SHEILA GERSHON
ZA Case Cleared 7/20/2020 SHEILA GERSHON
Grading Pre-Inspection Cleared 11/13/2020 PARISA ZAHABI

Contact Information

Contractor Vision Construction; Lic. No.: 541505-B 6012 TOPEKA DRIVE      TARZANA, CA 91356
Engineer Azizisefat,, Solayman; Lic. No.: C57840 19510 VENTURA BLVD STE 110      TARZANA, CA 91356

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/6/2021 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 1/7/2021 Conditional Approval RONALD COWAN
Pre-Gunite 1/7/2021 Conditional Approval RONALD COWAN
Deck 5/10/2021 Partial Approval MICHAEL PELHAM
Enclosure/Fence 8/9/2021 Partial Inspection RONALD COWAN
SGSOV-Seismic Gas S/O Valve 8/9/2021 SGSOV Not Ready RONALD COWAN
Enclosure/Fence 8/13/2021 Partial Approval RONALD COWAN
SGSOV-Seismic Gas S/O Valve 8/13/2021 SGSOV Not Ready RONALD COWAN
Final 8/25/2021 Corrections Issued PETER FOLLING
SGSOV-Seismic Gas S/O Valve 8/25/2021 SGSOV Not Ready PETER FOLLING
Pool Equipment Noise Test 9/2/2021 Approved FELIPE PENICHE
Final 9/10/2021 OK to Issue CofO RONALD COWAN
SGSOV-Seismic Gas S/O Valve 9/10/2021 SGSOV Approved RONALD COWAN