2260 S PELHAM AVE 90064
Certificate Information: 2260 S PELHAM AVE 90064
- Application / Permit
- 20047-30000-00940
- Plan Check / Job No.
- B20WL02668
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW PLUNGE POOL PER STD PLAN.
- Permit Issued
- Issued on 11/2/2020
- Issuing Office
- Current Status
- CofO Issued on 8/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2020 | RICARDO RAMIREZ |
| Corrections Issued | 6/29/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 7/28/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/30/2020 | KAVIAN REFAHI |
| Plan Check Approved | 11/2/2020 | KAVIAN REFAHI |
| Issued | 11/2/2020 | APPLICANT |
| Building Plans Picked Up | 11/2/2020 | APPLICANT |
| CofO in Progress | 7/22/2021 | GERMAN RODRIGUEZ MENDOZA |
| CofO Issued | 8/23/2021 | VINCENT COTTON |
| Permit Finaled | 8/23/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/28/2020 | RICARDO RAMIREZ |
| Construction near power lines | Cleared | 10/19/2020 | TORI CHEN |
Contact Information
| Architect | Lindfors,, Douglas A; Lic. No.: C27129 | 991 RICHARDSON AVENUE SIMI VALLEY, CA 93065 |
| Contractor | Santa Fe Contractors Inc; Lic. No.: 951293-B | 34385 ACTON CANYON RD ACTON, CA 93510 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1499 IRIS GROVE DR CORONA, CA 92881 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/19/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 11/25/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Gas Piping or Gas Test | 11/25/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Grounding or Bonding | 11/25/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Pool Piping | 11/25/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Pre-Gunite | 11/25/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Rough-Plumbing | 11/25/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Gas Piping or Gas Test | 12/3/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Enclosure/Fence | 2/22/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Enclosure/Fence | 2/23/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 3/4/2021 | SGSOV Not Ready | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 3/5/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Pool Equipment Noise Test | 3/8/2021 | Approved | DA LIU |
| Final | 3/10/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 3/10/2021 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 6/30/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |