11950 N ERWIN ST 91606

Certificate Information: 11950 N ERWIN ST 91606

Application / Permit
20047-30000-00918
Plan Check / Job No.
B20WL02606
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
Apartment
Primary Use
(4) Pool/Spa - Public
Work Description
New pool within existing cavity on level 3 podium deck (Bld'g A) per standard plan.
Permit Issued
Issued on 9/16/2020
Issuing Office
Current Status
Permit Finaled on 6/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2020 APPLICANT
Assigned to Plan Check Engineer 6/25/2020 MARJAN SHENASI
Corrections Issued 6/29/2020 MARJAN SHENASI
Plan Check Approved 9/16/2020 JASON JANGADA
Issued 9/16/2020 APPLICANT
Building Plans Picked Up 9/24/2020 APPLICANT
Permit Finaled 6/23/2023 ROBERT DAVIS

Permit Application Clearance Information

"Q" conditions Cleared 8/20/2020 MILENA ZASADZIEN
CPC Cleared 8/20/2020 MILENA ZASADZIEN
Historic Resource Verification Cleared 8/20/2020 MILENA ZASADZIEN
Miscellaneous Cleared 8/20/2020 MILENA ZASADZIEN
Redevelopment Project Area Cleared 8/20/2020 MILENA ZASADZIEN
Tract Map conditions Cleared 8/20/2020 MILENA ZASADZIEN
ZA Case Cleared 8/20/2020 MILENA ZASADZIEN
Sewer availability Cleared 8/21/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 8/25/2020 GUILLERMO PETRA
Public Swimming Pool approval Cleared 9/9/2020 LACDHS APPROVED

Contact Information

Contractor Aquatic Technologies; Lic. No.: 744177-C53 32232 PASEO ADELANTO STE A      SAN JUAN CAPISTRANO, CA 92675

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 7/7/2021 Conditional Approval ROBERT DAVIS
Enclosure/Fence 11/16/2021 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 1/24/2022 Approved ROBERT DAVIS
Final 1/24/2022 Not Ready for Inspection ROBERT DAVIS
Pre-Gunite 1/24/2022 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 1/24/2022 SGSOV Approved ROBERT DAVIS
Final 6/5/2023 Not Ready for Inspection ROBERT DAVIS
Final 6/20/2023 Not Ready for Inspection ANDREW DORSO
Special/Order Compliance 6/22/2023 Approved ROBERT DAVIS
Final 6/23/2023 Permit Finaled ROBERT DAVIS