6151 N RADFORD AVE 91606
Certificate Information: 6151 N RADFORD AVE 91606
- Application / Permit
- 20047-30000-00915
- Plan Check / Job No.
- B20WL02605
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- Apartment
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool within new apartment per standard plan. 47'-8" x 25'-6" 3'-6" - 4'-0" deep
- Permit Issued
- Issued on 11/20/2020
- Issuing Office
- Current Status
- Permit Finaled on 1/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 7/22/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 7/29/2020 | KAMRAN GHOTBI RAVANDI |
| Disabled Access Plans Picked Up | 8/4/2020 | APPLICANT |
| Plan Check Approved | 11/18/2020 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 11/19/2020 | APPLICANT |
| Issued | 11/20/2020 | APPLICANT |
| Permit Finaled | 1/3/2023 | ROBERT DAVIS |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 8/19/2020 | MICAELA TORRES-GIL |
| "Q" conditions | Cleared | 8/20/2020 | MILENA ZASADZIEN |
| Redevelopment Project Area | Cleared | 8/20/2020 | MILENA ZASADZIEN |
| ZA Case | Cleared | 8/20/2020 | MILENA ZASADZIEN |
| DAS Clearance | Cleared | 10/22/2020 | VLADIMIR ARUTYUNYAN |
| Public Swimming Pool approval | Cleared | 11/18/2020 | LACDHS APPROVED |
Contact Information
| Contractor | Aquatic Technologies; Lic. No.: 744177-B | 32232 PASEO ADELANTO STE A SAN JUAN CAPISTRANO, CA 92675 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/16/2021 | Conditional Approval | JOHN KITCKO |
| Enclosure/Fence | 10/17/2022 | Approved | ROBERT DAVIS |
| ELECTRICAL-Final | 11/29/2022 | Partial Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 11/29/2022 | Approved | ROBERT DAVIS |
| Final | 11/29/2022 | Not Ready for Inspection | ROBERT DAVIS |
| PLUMBING-Final | 11/29/2022 | Not Ready for Inspection | ROBERT DAVIS |
| Pre-Gunite | 11/29/2022 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Approved | ROBERT DAVIS |
| ELECTRICAL-Final | 1/3/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Final | 1/3/2023 | Permit Finaled | ROBERT DAVIS |
| PLUMBING-Final | 1/3/2023 | Not Ready for Inspection | ROBERT DAVIS |