7448 N CLAIRE AVE 91335
Certificate Information: 7448 N CLAIRE AVE 91335
- Application / Permit
- 20047-30000-00873
- Plan Check / Job No.
- B20WL02522
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool 13'- 0" x 24'- 0" w/ baja bench and spa 6'-0" x 6'-0" per standard plan # 268 at the side of the dwelling.
- Permit Issued
- Issued on 9/17/2020
- Issuing Office
- Current Status
- CofO Issued on 4/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2020 | JAHANSHAH POURHASSAN |
| Corrections Issued | 6/19/2020 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 7/9/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 7/28/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 8/12/2020 | PARISA ZAHABI |
| Plan Check Approved | 9/9/2020 | JASON JANGADA |
| Issued | 9/17/2020 | APPLICANT |
| Building Plans Picked Up | 9/18/2020 | APPLICANT |
| CofO in Progress | 4/1/2021 | VINCENT HANLEY |
| CofO Issued | 4/6/2021 | MICHAEL SMITH |
| Permit Finaled | 4/6/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/16/2020 | DENZEL HENDERSON |
Contact Information
| Contractor | Splash Pool Plastering Inc; Lic. No.: 979053-C53 | 15618 COBALT STREET SYLMAR, CA 91342 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 10/20/2020 | Not Ready for Inspection | SEAN WIRCH |
| Pre-Gunite | 11/23/2020 | Approved | VINCENT HANLEY |
| Deputy Shotcrete | 11/25/2020 | No Access for Inspection | VINCENT HANLEY |
| Deck | 12/23/2020 | Approved | VINCENT HANLEY |
| Deck | 2/11/2021 | Approved | VINCENT HANLEY |
| Enclosure/Fence | 2/11/2021 | Approved | VINCENT HANLEY |
| Pool Equipment Noise Test | 3/5/2021 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 3/31/2021 | Approved | VINCENT HANLEY |
| Final | 3/31/2021 | Partial Approval | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/31/2021 | SGSOV Approved | VINCENT HANLEY |