4136 S NEOSHO AVE 90066
Certificate Information: 4136 S NEOSHO AVE 90066
- Application / Permit
- 20047-30000-00837
- Plan Check / Job No.
- B20WL02437
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool, spa ( 24'x14.5') and pond. Per standard plans#270.
- Permit Issued
- Issued on 10/20/2020
- Issuing Office
- Current Status
- Issued on 10/20/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2020 | MARJAN SHENASI |
| Corrections Issued | 6/15/2020 | MARJAN SHENASI |
| Plan Check Approved | 9/30/2020 | ALFREDO JARA |
| Issued | 10/20/2020 | APPLICANT |
| Building Plans Picked Up | 10/21/2020 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 6/19/2020 | MAXFIELD VERMY |
| Construction near power lines | Cleared | 8/23/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/17/2020 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 12/11/2020 | Approved | JUAN VALENZUELA |
| Gas Piping or Gas Test | 12/11/2020 | Approved | JUAN VALENZUELA |
| Grounding or Bonding | 12/11/2020 | Approved | JUAN VALENZUELA |
| Pool Piping | 12/11/2020 | Approved | JUAN VALENZUELA |
| Pre-Gunite | 12/11/2020 | Approved | JUAN VALENZUELA |
| Rough-Plumbing | 12/11/2020 | Approved | JUAN VALENZUELA |
| Enclosure/Fence | 6/14/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Enclosure/Fence | 7/11/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Enclosure/Fence | 7/18/2022 | Approved | JESUS RODRIGUEZ |
| Final | 1/10/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/10/2023 | SGSOV Not Ready | HERBERT GIRON |