311 N SURFVIEW DR 90272
Certificate Information: 311 N SURFVIEW DR 90272
- Application / Permit
- 20047-30000-00804
- Plan Check / Job No.
- B20WL02367
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool and spa per std. plan # 265 at rear of the SFD.
- Permit Issued
- Issued on 2/3/2021
- Issuing Office
- Current Status
- CofO Issued on 7/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2020 | RICARDO RAMIREZ |
| Corrections Issued | 6/24/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 10/21/2020 | RICHARD GARCIA |
| Applicant returned to address corrections | 12/7/2020 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 12/22/2020 | MARJAN SHENASI |
| Applicant returned to address corrections | 1/21/2021 | JASON JANGADA |
| Plan Check Approved | 1/22/2021 | JASON JANGADA |
| Issued | 2/3/2021 | APPLICANT |
| Building Plans Picked Up | 2/4/2021 | APPLICANT |
| CofO in Progress | 7/1/2021 | ANDREW NAVE |
| Permit Finaled | 7/2/2021 | KENNETH NAGLE |
| CofO Issued | 7/2/2021 | KENNETH NAGLE |
| Permit Finaled | 7/2/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Coastal Zone | Cleared | 10/6/2020 | SARAHI ORTEGA |
| ZA Case | Cleared | 10/6/2020 | SARAHI ORTEGA |
| ZI | Cleared | 10/6/2020 | SARAHI ORTEGA |
| Grading Pre-Inspection | Cleared | 12/7/2020 | RICARDO RAMIREZ |
Contact Information
| Contractor | T & D Construction Unlimited Inc; Lic. No.: 1003171-B | 4107 EAST AVENUE S10 PALMDALE, CA 93552 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 3/31/2021 | Approved | ANDREW NAVE |
| Pre-Gunite | 3/31/2021 | Approved | ANDREW NAVE |
| Rough-Plumbing | 3/31/2021 | Approved | ANDREW NAVE |
| Deputy Shotcrete | 4/7/2021 | Conditional Approval | ANDREW NAVE |
| Grounding or Bonding | 5/3/2021 | Approved | ANDREW NAVE |
| Enclosure/Fence | 6/7/2021 | Approved | ANDREW NAVE |
| Equipment Noise Level | 6/18/2021 | Approved | JAMES VORHIS |
| Excavation/Setback/Form/Re-Bar | 6/29/2021 | Approved | ANDREW NAVE |
| Final | 6/29/2021 | Conditional Approval | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 6/29/2021 | SGSOV Approved | ANDREW NAVE |