2012 S CASTLE HEIGHTS AVE 90034
Certificate Information: 2012 S CASTLE HEIGHTS AVE 90034
- Application / Permit
- 20047-30000-00632
- Plan Check / Job No.
- B20WL02008
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) pool and spa 20'x32' Per standard plan #268.
- Permit Issued
- Issued on 5/27/2020
- Issuing Office
- Current Status
- CofO Issued on 2/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | KAVIAN REFAHI |
| Corrections Issued | 5/14/2020 | KAVIAN REFAHI |
| Plan Check Approved | 5/22/2020 | ALFREDO JARA |
| Issued | 5/27/2020 | APPLICANT |
| Building Plans Picked Up | 5/28/2020 | APPLICANT |
| CofO in Progress | 2/5/2021 | KENNETH NAGLE |
| Permit Finaled | 2/5/2021 | KENNETH NAGLE |
| CofO Issued | 2/5/2021 | KENNETH NAGLE |
| Permit Finaled | 2/5/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/14/2020 | KAVIAN REFAHI |
Contact Information
| Contractor | Sunset Built Inc; Lic. No.: 1005054-B | 5455 WILSHIRE BLVD #1811 LOS ANGELES, CA 90036 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/29/2020 | Conditional Approval | KEVIN SARGSYAN |
| Rough-Electrical | 6/29/2020 | Approved | KEVIN SARGSYAN |
| Rough-Plumbing | 6/29/2020 | Partial Approval | KEVIN SARGSYAN |
| Deputy Shotcrete | 7/2/2020 | Conditional Approval | KEVIN SARGSYAN |
| Gas Piping or Gas Test | 8/12/2020 | Corrections Issued | KEVIN SARGSYAN |
| Gas Piping or Gas Test | 8/13/2020 | Corrections Issued | KEVIN SARGSYAN |
| Gas Piping or Gas Test | 8/21/2020 | Approved | KEVIN SARGSYAN |
| Enclosure/Fence | 12/10/2020 | Corrections Issued | KEVIN SARGSYAN |
| Enclosure/Fence | 12/11/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Enclosure/Fence | 12/16/2020 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 12/29/2020 | Approved | KEVIN SARGSYAN |
| Final | 12/29/2020 | Corrections Issued | KEVIN SARGSYAN |
| Pool Equipment Noise Test | 12/29/2020 | Approved | ROBERT CHAVEZ |
| Pre-Gunite | 12/29/2020 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 12/29/2020 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 1/13/2021 | Conditional Approval | KEVIN SARGSYAN |